•  2014 Bond District-Wide Improvements
    Projects by School                           


     District - Wide
         I - Site Improvements
                            Parking Lot Assessment Report - Complete
         III - Furniture/Fixtures/Equipment - Complete                        


     Athey Creek
         IV - Roofing / Exterior Envelope
                            Select Roof Replacement - Complete
         V - Mechanical/Electrical/Plumbing 
                            Ground AHU Motors
                            Gymnasium AHU replacement
                            Individual Boiler Venting
                            Install VFD's for Multizone Unit
                            Remove Old Domestic Water Storage Tank
                            Replace Gym Lights - Complete
                            Select VFD Replacement

     Boeckman Creek
         II - Interior Improvements
                            Remodel Office - Complete
                            Replace Partitions with Permanent Walls - Complete
                            Select Corridor Carpet Replacement - Complete
                            Select Restroom Renovation - Complete
                            Refinish Porch/Corridor Walls
         IV - Roofing / Exterior Envelope
                            Select Roof Replacement - Complete
         V - Mechanical/Electrical/Plumbing
                            Lighting Replacement
                            Replace Boiler Room Controls with DDC
                            Replace Commons Lights - Complete
                            Replace Cooler Tower
                            Replace Fire Sprinkler System - Complete
                            Replace Gym Lights - Complete
                            Upgrade HVAC Control Boards

     Bolton
         II - Interior Improvements
                            Remodel Office- Complete
                            Renovate Lower Level Locker Rooms - Complete
                            Renovate Select Classrooms - Complete
                            New Music Room
         IV - Roofing / Exterior Envelope
                            Replace Cafeteria Windows - Complete
          V - Mechanical/Electrical/Plumbing
                            Controls for Classroom Exhaust Fans
                            Replace Gym Lights - Complete

     Boones Ferry
         I - Site Improvements
                            Building Signage - Complete
         II - Interior Improvements
                            Replace Office and Staff Room Carpet - Complete
         III - Furniture/Fixtures/Equipment
                            Replace Dishwasher (Main Kitchen) - Complete
         V - Mechanical/Electrical/Plumbing
                            Install Isolation Valves on Heating Water System
                            Replace Refrigeration Lines for Freezers

     Cedaroak Park
         I - Site Improvements
                            Perimeter Fencing - Complete
                            Refinish Entry Canopy
        II - Interior Improvements
                            Replace carpet in classrooms and porches
        IV - Roofing / Exterior Envelope
                            Gym Roof Replacement - Complete
         V - Mechanical/Electrical/Plumbing
                            Replace Gym Lights - Complete
                            Replace Gym Unit Ventilators
                            Replace PRV System
                            Upgrade Controls to DDC

     Inza Wood
          I - Site Improvements
                           Track / Field Replacement & Field Lighting
         II - Interior Improvements
                            Replace Classroom Carpet - Complete
                            Replace Library area Carpet - Complete
                            Courtyard Entry
         IV - Roofing / Exterior Envelope
                            Select Roof Replacement - Complete
         V - Mechanical/Electrical/Plumbing
                            Replace Boilers / Isolate Vibration
                            Replace Gym Lights - Complete
                            Replace Isolation Valves
                            Upgrade Controls to DDC
                            Upgrade VAV Controls to DDC

     Rosemont Ridge
         I - Site Improvements
                            Additional Drainage at Baseball Field - Complete
                            New Play Equipment - Complete
                            Women's Softball Storage, Restrooms - Complete
         IV - Roofing / Exterior Envelope
                            Select Roof Replacement - Complete
         V - Mechanical/Electrical/Plumbing
                            Ground VFD Motors
                            Replace Commons Lights - Complete
                            Replace Gym Lights - Complete
                            Upgrade Fire Panel

     Stafford
         I - Site Improvements
                            New Play Equipment / Add Drainage - Complete
         II - Interior Improvements
                            Select Restroom Renovation - Complete
         IV - Roofing / Exterior Envelope
                            Library and Office Roofing Replacement - Complete
         V - Mechanical/Electrical/Plumbing
                            Add Wall Packs Around Building Exterior
                            Replace Freezers
                            Replace Gym Lights - Complete
                            Replace Gym Unit - Complete
                            Replace Multi-Purpose Rooms Lights
     
     Trillium Creek
        II - Interior Improvements
                            Classroom Enclosure - Complete

     West Linn High School
         I - Site Improvements
                            Crosswalk Flasher Power
                            Resurface Tennis Courts
                            Track and Field Improvements - Complete
                            Turf Baseball Field - Complete
                            New Entry Door - Complete
        II - Interior Improvements
                            Library Glazing - Complete
                            Tech / STEM Classroom Renovation - Complete
                            New Gym Bleachers
         V - Mechanical/Electrical/Plumbing
                            Add Wall Packs Near Gym/Boiler Room - Complete
                            Replace Clock and Bell System - Complete
                            Replace Damaged Fire Sprinkler Pipe (MIC)
                            Replace Domestic Hot Water Heater
                            Replace Gym Lights (Main Gym) - Complete
                            Replace Heating Water Heaters

     Willamette
         I - Site Improvements
                            New Play Equipment - Complete
         II - Interior Improvements
                            Corridor Painting - Complete 
                            Replace Classroom Carpet - Complete
                            Replace Hallway Carpet - Complete
         IV - Roofing / Exterior Envelope
                            Slope Roofing at Cafeteria - Complete
         V - Mechanical/Electrical/Plumbing
                            Add Wall Packs Around Building Exterior
                            Replace Gym Lights - Complete
                            Replace Gym Units
                            Sump Pump and Tamper Circuit at Fire Vault - Complete
                            Upgrade Pneumatic Controls to DDC

     Wilsonville High School
         I - Site Improvements
                            Paint Stadium - Complete
                            Select Sidewalk Replacement at Stadium - Complete
                            Resurface Tennis Courts
                            Turf Baseball Fields, JV & Varsity - Complete
                            Add Softball Field Lighting
                            New Entry Door & Courtyard - Complete
         II - Interior Improvements
                            Replace Gym Scoreboards - Complete
                            Replace Select Space Carpet - Complete
                            Refurbish Main Gym Restrooms - Complete
         III - Furniture/Fixtures/Equipment
                            Replace Dishwasher (Main Kitchen) - Complete
                            Replace Kitchen Equipment - Complete
         IV - Roofing / Exterior Envelope
                            Select Roof Replacement - Complete
         V - Mechanical/Electrical/Plumbing
                            Gym Lighting Replacement (Main Gym) - Complete
                            Replace Fire Alarm System - Complete
                            Replace Rolling Fire Doors with Swinging
     
     
     DW Pie Chart