• 15008 Drainage & Play Equipment 

    Drainage and Play Equipment at Stafford, Rosemont Ridge and Willamette includes replacing play equipment at Willamette, Rosemont Ridge and Stafford as well as adding needed drainage to Stafford's playground and Rosemont Baseball Field.

  • Work Complete

    Posted by Amy Berger on 10/12/2016

    Contracts have been secured for all work. Work is complete at Rosemont Ridge Middle School and Stafford Primary School. The Willamette Primary PTA provided funds for additional play equipment, which will be installed in October.

    Comments (-1)
  • Work on Schedule

    Posted by Amy Berger on 8/10/2016

    The contracts for all three schools, Stafford Primary, Willamette Primary and Rosemont Ridge Middle Schools have been executed and work is proceeding on schedule.

    Comments (-1)
  • Drainage & Play Equipment Update

    Posted by Amy Berger on 4/20/2016

    The play equipment was purchased and delivered to the district. All remaining project scope has been bid, and the Bond Management Team is working to secure contracts for construction. Construction to occur during summer 2016.

    Comments (-1)
  • Project to be Re-Bid

    Posted by Amy Berger on 10/19/2015

    The play equipment was purchased and delivered to the district. The play equipment installation and Stafford Primary drainage work was publicly bid with no acceptable bids received. The procurement strategy is being reviewed and will likely be bid again in late winter or early spring.

    The space net was installed and baseball field drainage has been completed at Rosemont Ridge Middle School.

     

     

     

    Comments (-1)