• 18054 - Track Replacement @ Wood Middle School

    This project includes the removal and replacement of the aging athletic track and underlying pavement. The pavement contract has been executed, and the track surfacing contract is expected to be presented to the Board in April. The work is planned for summer 2019.

  • Quarterly Report Update

    Posted by Amy Berger on 7/12/2019

    Bids were received and a construction contract was executed. Excavation of the existing material is complete and base rock has been installed.

    Comments (-1)
  • Quarterly Report Update

    Posted by Amy Berger on 4/23/2019

    The pavement contract has been executed and the track surfacing contract is expected to be presented to the Board in April. The work is planned for summer 2019.