• 18063 - Music Room @ Bolton Primary School

    This project includes the abatement and demolition of two existing classrooms, the creation of a new acoustically attenuated music room with associated storage and a conference room.

  • Quarterly Report Update

    Posted by Amy Berger on 7/12/2019

    Pricing was received and approved for abatement and construction. Abatement is complete and construction is underway.

    Comments (-1)
  • Quarterly Report Update

    Posted by Amy Berger on 4/23/2019

    The design is expected to be complete in the coming days. The work is planned for summer 2019.

    Comments (-1)