WHS Performing Arts Center
Page Navigation
2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023
Recent Activities:
■ Phase 4 is underway, which includes the Black Box and old theater conversion to CTE spaces
■ Old auditorium in-fill is complete and structural work is underway
■ Theater rigging sytems inspections have been completed
■ Required firewall work is currently underway
■ Electrical rough in has started in teh new CTE spaces
■ Final accoustical treatments have been installed
■ Roof repairs have begun
■ Final site plantings are underway
Upcoming Activities:
■ Mechanical rough-in in the CTE space
■ Stud framing work to begin on the new interior walls for the new CTE and Black Box spaces
■ Installation of exterior building signage
■ Additional mechanical screen wall work
■ Existing exterior wall corrective work
■ Final site work