2023 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 7/20/2023

Recent Activities:
  Phase 4 is underway, which includes the Black Box and old theater conversion to CTE spaces
    Old auditorium in-fill is complete and structural work is underway
    Theater rigging sytems inspections have been completed
    Required firewall work is currently underway
    Electrical rough in has started in teh new CTE spaces
    Final accoustical treatments have been installed
    Roof repairs have begun
    Final site plantings are underway

Upcoming Activities:
    Mechanical rough-in in the CTE space
    Stud framing work to begin on the new interior walls for the new CTE and Black Box spaces
    Installation of exterior building signage
    Additional mechanical screen wall work
    Existing exterior wall corrective work
    Final site work