Recent Activities:
■ City of West Linn Planning Commission approved the project with conditions in August
■ Willamette Neighborhood Association appealed the Planning Commission decision
■ Permit drawing set completed in July and submitted to the City of West Linn Building Department
■ Advertisement to pre-qualify bidders sent to the DJC, qualifying method approved by the School Board
■ Continued collaboration for the City’s portion of the right of way work along Willamette Falls Drive
■ Furniture layouts and design meetings continue
Upcoming Activities:
■ Contractor proposals due October 6th, review period October 7-15 and the list of qualified contractors released
October 15th
■ Advertise to bid the project October 20th with bids due December 8th
■ City Council Meeting set for October 4th
■ Final decision from West Linn City Council meeting
New Arts Porch Rendering
Athey Idol Rendering from upper commons looking down
Lower level makerspace porch
Porch Rendering
Recent
By Month
- January 2024
- October 2023
- July 2023
- April 2023
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- July 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- August 2021
- April 2021
- March 2021
- February 2021
- January 2021
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- February 2020