Athey Creek Middle School At Dollar
Project Update March 14, 2022
Posted by West Linn - Wilsonville School District on 3/14/2022
- The General Contractor mobilized to the site in January. General site clearing occurred in January, allowing for general excavation.
- The excavation to lower the site is underway.
- A temporary road off Willamette Falls Drive has been built to allow major construction traffic access and keep larger vehicles off Dollar Street as much as possible.
- A secondary access road has been built off Dollar Street, but the primary construction vehicle access is off Willamette Falls drive.
- The Contractor is preparing a new staging and onsite parking area and will reduce contractor parking along the street.
- The construction hours are required to align with the City Noise Ordinance. The times noted are in the City Municipal Code.
- For any questions or concerns about the project, please contact the District’s Project Manager, Angela Caffrey 503-673-7315 ext. 4975
By Month
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- July 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- August 2021
- April 2021
- March 2021
- February 2021
- January 2021
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- February 2020