Project Update March 14, 2022

Posted by West Linn - Wilsonville School District on 3/14/2022

  • The General Contractor mobilized to the site in January. General site clearing occurred in January, allowing for general excavation.
  • The excavation to lower the site is underway.
  • A temporary road off Willamette Falls Drive has been built to allow major construction traffic access and keep larger vehicles off Dollar Street as much as possible.
  • A secondary access road has been built off Dollar Street, but the primary construction vehicle access is off Willamette Falls drive.
  • The Contractor is preparing a new staging and onsite parking area and will reduce contractor parking along the street.
  • The construction hours are required to align with the City Noise Ordinance. The times noted are in the City Municipal Code.
  • For any questions or concerns about the project, please contact the District’s Project Manager, Angela Caffrey 503-673-7315 ext. 4975

Site work