2023 Q1 Project Updates

Posted by West Linn - Wilsonville School District on 4/20/2023

Interior stairs

Recent Activities:
    Structural steel erection is complete, including covered entry areas and bus canopies. Bus canopies will be finalized with translucent solar panels in the spring.
    Interior metal stud framing is nearly complete, with drywall installation beginning in selected areas.
    The temporary roof has been completed, with the exception of the large expansion joint area between the commons and classroom wings. Final roof installation is occurring as weather permits. 
    Major plumbing, HVAC and Electrical components are being installed, including electrical switchgear, boilers, terminal units and rooftop mechanical units.
    Exterior window frame installation is in progress and will frame the main entry to the building.
    The City of West Linn has assigned the new address: 2110 Brandon Place.
    Water line installation on Willamette Falls DRive is complete and retaining wall installation on the north side of Willamette Falls DRive is in progress.
    New curbs are installed on the new Brandon Place extension, and the intersection of Brandon Place and Dollar Street is being prepared for final asphalt.
    The moving company was hired and Athey CReek staff have begun packing for the move this summer. 
    Elevator installation has begun

Upcoming Activities:
    Final paving on Dollar Street was delayed due to weather but is anticipated to occur in April.
    Reconstruction of the West entry to Fields Bridge Park and continued work on the north side of Willamette Falls Drive, including new street lights, bike paths, and sidewalks
    Interior finish work will commence in the building this spring, including drywall, casework, tiling and paint.
    Parking lots and track work to commence later in the spring.
    Permanent power will be installed to the building in April.