2024 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 11/19/2024
Recent Activities:
■ Permanent track surfacing was completed over the summer and the new scoreboard was installed
■ Landscaping continues. Sloped areas have been planted with seed mixes
■ Public Street Improvements (grading, retaining walls, sidewalks, bike lanes, crosswalks, pedestrian flashers, street lighting and storm drainage) has continued over the summer. Final road paving occurred at the end of September
Upcoming Activities:
■ Landscaping and bike lanes will be completed with the remaining work on Willamette Falls Drive
■ Remaining trees and plantings along Willamette Falls Drive will occur through the fall, along with irrigation
■ Biweekly meetings with the City of West Linn will continue through the project completion
Recent
By Month
- November 2024
- July 2024
- April 2024
- January 2024
- October 2023
- July 2023
- April 2023
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- July 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- August 2021
- April 2021
- March 2021
- February 2021
- January 2021
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- February 2020