2021 Q3 Project Updates

Posted by West Linn - Wilsonville School District on 10/21/2021

New office construction

New Office Addition

Recent Activities:
■ New MDF and IDF is complete
■ Data rewire is approximately 70% complete, with the remainder to take place during phase 2 of the project
■ New front entry plaza has begun construction, temporary access provided for school
■ All structural steel on the new entry is complete and framing walls is underway

Upcoming Activities:
■ Rough in for Mechanical, Electrical, and Plumbing to occur late October
■ Roof installation
■ Air handling unit replacement during Thanksgiving break
■ Well system shutdown, cleaning and inspection and control system upgrades during Winter break