2022 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 7/22/2022

Office Construction

Recent Activities:
■ Existing office space demolition is complete
■ Currently framing in single occupant restrooms and conference rooms
■ Mechanical, Electrical and Plumbing rough-in work has begun in the existing office space
■ Science hall roof well work has begun
■ Additional roof work and building envelope nearing completion
■ Punch list work has begun on new office space

Upcoming Activities:
■ Substantial completion of current construction is expected at the
end of August 2022
■ Design for final phase of work, scheduled for construction
summer of 2023