2021 Quarter 1 Project Updates

Posted by West Linn - Wilsonville School District on 4/22/2021

19034.011 – Renovation at Wood Middle School
Project Status:
Project has been advertised and awarded. Contractor mobilization is expected spring 2021. Logistics planning to ensure separation of construction and school activities underway.
■ Low bid below budget and estimate
■ Board authorized selection of all project scope

19049.009 – Renovations at Stafford Primary School & Willamette Primary School
Project Status:
The project was bid and a general contractor was awarded the project in February. The low bid was over budget but near the estimate. The School Board authorized selection of the base bid. This project is scheduled to start construction this summer.

19050.009 – Renovations at Bolton Primary School and Cedaroak Park Primary School
Project Status:
The project was bid and a general contractor was awarded the project in February. The low bid was over budget but near the estimate. The School Board authorized selection of the base bid. This project is scheduled to start construction this summer.