- 2019 Capital Bond
- Project Updates
Facility Updates
2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/2023
19039.018 – Security Upgrades at Trillium Creek Primary School
Project Status:
This project includes creating a secure entry vestibule and improved classroom lockdown capability.
Recent Activities:
- This project bid and has an executed contract in place, work to begin summer 2023
19054.017 – Fire Sprinklers at Boeckman Creek Primary School
Project Status:
This project includes fire sprinkler main line replacement at Boeckman Creek Primary School.
Recent Activities:
- This project is complete. Final testing occurred and is complete.
19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools
Project Status:
This project includes security curtains and improved classroom lockdown capabilities at these three schools.
Recent Activities:
- The project is currently in design
Upcoming Activities:
- Bidding in Spring 2023 with construction to occur Summer 2023