2022 Q4 Project Updates

Posted by West Linn - Wilsonville School District on 2/3/2023

19039.018 – Security Upgrades at Trillium Creek Primary School

Project Status:

This project includes creating a secure entry vestibule and improved classroom lockdown capability.

 Recent Activities:

  • This project bid and has an executed contract in place, work to begin summer 2023

 

19054.017 – Fire Sprinklers at Boeckman Creek Primary School

Project Status:

This project includes fire sprinkler main line replacement at Boeckman Creek Primary School.

 Recent Activities:

  • This project is complete. Final testing occurred and is complete.

 

19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools

Project Status:

This project includes security curtains and improved classroom lockdown capabilities at these three schools.

 Recent Activities:

  • The project is currently in design

Upcoming Activities:

  • Bidding in Spring 2023 with construction to occur Summer 2023