• Learning with Technology
  • 2022 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/28/2022

    Recent Activities:
    ■ Deployment of UPS equipment in wiring closets is nearing completion
    ■ Prep for wiring projects at Boeckman Creek and Stafford Primary Schools for work this summer
    ■ Digital signage projects at Rosemont Ridge, Meridian Creek and Inza Wood MIddle Schools
    ■ Printer fleet replacement has begun districtwide
    ■ E-Rate program filing is up to date to support the update of the wifi scheduled for this summer


    Upcoming Activities:
    ■ WIFI update coming summer 2022
    ■ Replacement of approximately 4,000 Chromebooks summer 2022
    ■ Wiring projects at Boeckman Creek and Stafford Primary Schools bids will be received in April, work to happen Summer 2022

    Comments (-1)
  • 2021 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/21/2022

    Recent Activities:
    ■ Finishing the installation of new network electronics
    ■ Starting printer fleet replacement
    ■ Digital signage beginning
    ■ E-Rate program reimbursements for technology purchases were receeived


    Upcoming Activities:
    ■ WIFI update coming summer 2022
    ■ Replacement of approximately 4,000 Chromebooks summer 2022
    ■ Printer fleet replacement spring 2022

    Comments (-1)
  • 2021 Quarter 1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/22/2021

    Recent Activities:
    ■ Nearing completion of new clock system delopoments
    ■ Currently working on intercom enhancements
    ■ Student and staff device purchase and setup
    ■ Server environment replacement
    ■ Network electronics equipment purchase


    Upcoming Activities:
    ■ 2021 device replacement planning
    ■ Network electronics installation

    Comments (-1)
  • Quarter 4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/2/2021

    Recent Activities:
    ■ Phone system installation and setup
    ■ Student and staff device purchase and setup
    ■ Server environment replacement


    Upcoming Activities:
    ■ Network electronics updates planning
    ■ 2021 device replacement planning

    Comments (-1)
  • Quarter 3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/28/2020

    Recent Activities:

    • Phone system installation and setup
    • Student and staff device purchase and setup
    • Server environment replacement

    Upcoming Activities:

    • Student and staff device purchase and setup
    • Perparation for 2021 projects
    Comments (-1)
  • Quarterly Updates

    Posted by Amy Berger on 7/27/2020

    Recent Activities:

    ■ Selection, purchase and training for new student information system

    ■ Phone system replacement selection, purchase and launch of installation

    ■ Student and staff device purchase and setup

     

    Upcoming Activities:

    ■ Phone system installation and setup

    ■ Student and staff device purchase and setup

    ■ Server environment replacement

    Comments (-1)