- 2019 Capital Bond
- Project Updates
-
Learning with Technology
-
2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023Recent Activities:
■ Implentation of technology needs at the new schools, Athey Creek and RIverside High
■ Wifi updates
■ Device replacements
■ Digital display installationsUpcoming Activities:
■ Implentation of technology needs at new schools, Athey Creek and Riverside High
■ Acquisition of Chromebooks around the District
■ Digital display installations -
2023 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/20/2023Recent Activies:
■ Security updates across the district
■ Additional intercom enhancements
■ Implementation of additional digital signageUpcoming Activies:
■ Acquisition of technology needs at new schools, Athey Creek and Riverside High Schools
■ Acquisition of Chromebooks around the district
■ Purchase of additional presentation systems
■ Wifi updates will continue -
2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/2023Recent Activities:
- Security updates across the district
- Wifi updates are about 90% complete
- Implementation of additional digital signage
Upcoming Activities:
- Planning for acquisition of technology needs at new schools, Athey Creek and Riverside High
- Purchase of additional presentation systems
- Wifi updates will continue
-
2022 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/22/2022Recent Activities:
■ Deployment of additional flat-screen Classroom Display Systems
■ Orders placed for 3,500 Chromebooks to replace existing units at end of life
■ Security updates across the district
■ Re-wiring projects at Boeckman Creek and Stafford Primary Schools is underway
Upcoming Activities:
■ Continuing updating end of life Chromebooks districtwide
■ Printer Fleet replacement continues with supply chain issues
■ Wifi updates have begun with delays due to supply chain issues -
2022 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/28/2022Recent Activities:
■ Deployment of UPS equipment in wiring closets is nearing completion
■ Prep for wiring projects at Boeckman Creek and Stafford Primary Schools for work this summer
■ Digital signage projects at Rosemont Ridge, Meridian Creek and Inza Wood MIddle Schools
■ Printer fleet replacement has begun districtwide
■ E-Rate program filing is up to date to support the update of the wifi scheduled for this summer
Upcoming Activities:
■ WIFI update coming summer 2022
■ Replacement of approximately 4,000 Chromebooks summer 2022
■ Wiring projects at Boeckman Creek and Stafford Primary Schools bids will be received in April, work to happen Summer 2022 -
2021 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 1/21/2022Recent Activities:
■ Finishing the installation of new network electronics
■ Starting printer fleet replacement
■ Digital signage beginning
■ E-Rate program reimbursements for technology purchases were receeived
Upcoming Activities:
■ WIFI update coming summer 2022
■ Replacement of approximately 4,000 Chromebooks summer 2022
■ Printer fleet replacement spring 2022 -
2021 Quarter 1 Project Updates
Posted by West Linn - Wilsonville School District on 4/22/2021Recent Activities:
■ Nearing completion of new clock system delopoments
■ Currently working on intercom enhancements
■ Student and staff device purchase and setup
■ Server environment replacement
■ Network electronics equipment purchase
Upcoming Activities:
■ 2021 device replacement planning
■ Network electronics installation -
Quarter 4 Project Updates
Posted by West Linn - Wilsonville School District on 2/2/2021Recent Activities:
■ Phone system installation and setup
■ Student and staff device purchase and setup
■ Server environment replacement
Upcoming Activities:
■ Network electronics updates planning
■ 2021 device replacement planning -
Quarter 3 Project Updates
Posted by West Linn - Wilsonville School District on 10/28/2020Recent Activities:
- Phone system installation and setup
- Student and staff device purchase and setup
- Server environment replacement
Upcoming Activities:
- Student and staff device purchase and setup
- Perparation for 2021 projects
-
Quarterly Updates
Posted by Amy Berger on 7/27/2020Recent Activities:
■ Selection, purchase and training for new student information system
■ Phone system replacement selection, purchase and launch of installation
■ Student and staff device purchase and setup
Upcoming Activities:
■ Phone system installation and setup
■ Student and staff device purchase and setup
■ Server environment replacement