• 2021 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 8/4/2021

    Recent Activities:
    ■ Notice to proceed issued to contractor in April
    ■ Contractor began early site mobilization late April
    ■ Parking lot, plaza and stadium seating work began
    ■ Storm drain work in the bus loop to began re-route the storm line
    ■ Building permit received late June
    ■ Work fully underway after release of school for the summer late June

    Upcoming Activities:
    ■ Work on the corner of West A Street and Skyline scheduled for completion in July
    ■ Added work in the bus loop scheduled for completion prior to start of school
    ■ Stadium seating area scheduled for completion end of September
    ■ Completion of the Parking lot and Plaza scheduled for October

    Ariel photo of construction

    Comments (-1)
  • WLHS Stadium Project

    Posted by West Linn - Wilsonville School District on 6/14/2021
    We have two updates to share regarding the West Linn High School Stadium Project. 
     
    Considerable progress has been made in clearing out the site for the new parking lot. Fabric and the first layer of rock is being installed at areas where finish grade has already been met. Excavation for the new plaza adjacent the existing stadium has begun. The track is being protected during this process to allow for heavy equipment to access the stadium for improvements.
     
    We would also like to remind the community that the entire track and field area are closed to the school and to the public during construction. 
     
    This closure will extend through the summer and into the early fall for public safety. Closure signs have been posted around the site to remind community members and the district asks that the public observe the closure during construction. Thank you for your patience and partnership as we complete these improvements that will serve the greater community for years to come. 
     
    WLHS Site Work
     
    WLHS Site Work
     
    WLHS Site Work
    Comments (-1)
  • Site Work

    Posted by West Linn - Wilsonville School District on 5/7/2021

    WLHS Site Plan

    Construction update for WLHS Stadium & Parking Expansion: The General contractor mobilized last week and began securing the Phase 1 area of Construction. The first stage of permitting has been approved to allow tree removal to commence beginning on Friday, May 7th. Clearing for the new parking area is expected to continue for the next couple of weeks.

     
    Any questions please contact the project manager:
    Angela Caffrey
    caffreya@wlwv.k12.or.us
    Comments (-1)
  • 2021 Quarter 1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/22/2021

    Recent Activities:
    ■ Land Use Application approved, permit review in progress
    ■ Contractor solicitation complete and contract has been fully executed
    ■ Low bid below budget and estimate
    ■ Board authorized selection of base bid and additive alternate #1 to build the full north parking addition


    Upcoming Activities:
    ■ Permit issuance
    ■ Contractor mobilization and construction start

    Comments (-1)
  • WLHS Stadium Project Work Started

    Posted by West Linn - Wilsonville School District on 4/21/2021
    The contractor at WLHS has mobilized on site and is preparing erosion control and initial clearing.
     
    Construction hours in the City of West Linn are Monday-Friday 7am-7pm, Saturday and Sunday 9am-5pm.
     
     
    If you have any questions please contact the Project Manager.
     
    Angela Caffrey
     
    Site Construction
    Comments (-1)
  • WLHS Pre-Bid Conference Location

    Posted by West Linn - Wilsonville School District on 2/9/2021

    Meeting location for WLHS Stadium project pre bid:

    WLHS Site Map

    Comments (-1)
  • Quarter 4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/2/2021

    Recent Activities:
    ■ Design committee comprised of District and School leadership, and community members met regularly
    ■ Land Use Application Submitted to City


    Upcoming Activities:
    ■ Design committee comprised of District and School leadership, and community members meet regularly
    ■ Construction Document Design Phase complete early February 2021
    ■ Project out to bid February 2021

    Stadium Lansdcape and path rendering

    Comments (-1)
  • Quarter 3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/28/2020

    Recent Activities:

    • Design committee comprised of District and School leadership, and community members met regularly
    • Design presented at Community Meetings July 15, 21 and 30, 2020
    • Design Development phase of design complete
    • Land Use Application Submitted to City

    Upcoming Activities:

    • Design committee comprised of District and School leadership
    Comments (-1)
  • Project Update

    Posted by West Linn - Wilsonville School District on 9/25/2020

    Design presentations for the WLHS Stadium Expansion and New North Parking Lot were provided to the community via Zoom on 7/16, 7/21 and 7/30. The project team is preparing to submit design concept documents to the City of West Linn for Land Use Review. The final design is scheduled to be complete by February 2021, with construction occurring spring-summer 2021.

    Stadium Rendering

     

    WLHS Rendering Plaza

    Comments (-1)
  • July 30 WLHS Stadium Community Engagement Meeting Information

    Posted by Amy Berger on 7/29/2020

    Below is the meeting information to access the July 30 Community Engagement Meeting. The meeting will begin at 6 p.m. and will include time for public questions and input.

    The meeting will be recorded and posted to the district website following the meeting. Community members who are unable to attend the meeting will be able to provide input through an Online Survey that is posted to the bond website. To learn more about the project, please visit the bond website.

    Join online: https://cbre.zoom.us/j/94980135157

    Join by phone: +1-669-900-6833 Meeting ID: 949 8013 5157

    Comments (-1)