• WLHS Stadium Project Update

    Posted by West Linn - Wilsonville School District on 11/15/2021

    WLHS STADIUM & PARKING EXPANSION – PROJECT UPDATE

    Air photo of site

    Raising the Roof! There have been product delays that have kept the stadium from completing in October as originally scheduled, however the project is moving forward. The stadium roof structure shipped in from Idaho, and the installation of the sheet metal roofing is near completion. The new restrooms, stadium seating, and updated press rooms are all getting finishing touches. The field lights have been operational since September, which has allowed evening soccer and other games to occur.

    The addition of storm drain work in the bus loop consumed contractor resources and shifted the priority toward the reopening of the bus loop in time for school to start. Though the contractors did make the bus loop deadline the ability to concurrently complete the stadium in time for football playoffs did not materialize.

    The new parking lot and plaza have a subterranean drainage system consisting of a series of tanks. These tanks were delayed which led to a series of design changes and ultimately, schedule loss. This new system is designed to intercept and treat rain water from the parking lot and hillside, which will not only clean water return to the river but prevent it from streaming into the stadium and track.

    When the parking lot is complete it will be connected to the stadium with a new plaza which will provide new spaces for students during the school day and the community to gather during sporting events. The General Contractor continues to try and improve the schedule with creative means.

    Comments (-1)
  • 2021 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/21/2021

    Aerial Photo of stadium and new courtyard

    Recent Activities:
    ■ Bus loop storm drain installation complete and opened on time for school
    ■ Concrete stadium step installation complete, plaza work began in September
    ■ New stadium seating was installed on the north side of the field
    ■ Stadium field lighting was completed in September
    ■ Working on contracting for a new fire alarm system for the stadium


    Upcoming Activities:
    ■ Stadium steel roof beams and columns arriving for install in October
    ■ Parking lot asphalt scheduled for mid November
    ■ Parking lot completion scheduled for early December
    ■ New audio-visual system to be installed

    Aerial photo of new parking lot and plaza

    Comments (-1)
  • 2021 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 8/4/2021

    Recent Activities:
    ■ Notice to proceed issued to contractor in April
    ■ Contractor began early site mobilization late April
    ■ Parking lot, plaza and stadium seating work began
    ■ Storm drain work in the bus loop to began re-route the storm line
    ■ Building permit received late June
    ■ Work fully underway after release of school for the summer late June

    Upcoming Activities:
    ■ Work on the corner of West A Street and Skyline scheduled for completion in July
    ■ Added work in the bus loop scheduled for completion prior to start of school
    ■ Stadium seating area scheduled for completion end of September
    ■ Completion of the Parking lot and Plaza scheduled for October

    Ariel photo of construction

    Comments (-1)
  • WLHS Stadium Project

    Posted by West Linn - Wilsonville School District on 6/14/2021
    We have two updates to share regarding the West Linn High School Stadium Project. 
     
    Considerable progress has been made in clearing out the site for the new parking lot. Fabric and the first layer of rock is being installed at areas where finish grade has already been met. Excavation for the new plaza adjacent the existing stadium has begun. The track is being protected during this process to allow for heavy equipment to access the stadium for improvements.
     
    We would also like to remind the community that the entire track and field area are closed to the school and to the public during construction. 
     
    This closure will extend through the summer and into the early fall for public safety. Closure signs have been posted around the site to remind community members and the district asks that the public observe the closure during construction. Thank you for your patience and partnership as we complete these improvements that will serve the greater community for years to come. 
     
    WLHS Site Work
     
    WLHS Site Work
     
    WLHS Site Work
    Comments (-1)
  • Site Work

    Posted by West Linn - Wilsonville School District on 5/7/2021

    WLHS Site Plan

    Construction update for WLHS Stadium & Parking Expansion: The General contractor mobilized last week and began securing the Phase 1 area of Construction. The first stage of permitting has been approved to allow tree removal to commence beginning on Friday, May 7th. Clearing for the new parking area is expected to continue for the next couple of weeks.

     
    Any questions please contact the project manager:
    Angela Caffrey
    caffreya@wlwv.k12.or.us
    Comments (-1)
  • 2021 Quarter 1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/22/2021

    Recent Activities:
    ■ Land Use Application approved, permit review in progress
    ■ Contractor solicitation complete and contract has been fully executed
    ■ Low bid below budget and estimate
    ■ Board authorized selection of base bid and additive alternate #1 to build the full north parking addition


    Upcoming Activities:
    ■ Permit issuance
    ■ Contractor mobilization and construction start

    Comments (-1)
  • WLHS Stadium Project Work Started

    Posted by West Linn - Wilsonville School District on 4/21/2021
    The contractor at WLHS has mobilized on site and is preparing erosion control and initial clearing.
     
    Construction hours in the City of West Linn are Monday-Friday 7am-7pm, Saturday and Sunday 9am-5pm.
     
     
    If you have any questions please contact the Project Manager.
     
    Angela Caffrey
     
    Site Construction
    Comments (-1)
  • WLHS Pre-Bid Conference Location

    Posted by West Linn - Wilsonville School District on 2/9/2021

    Meeting location for WLHS Stadium project pre bid:

    WLHS Site Map

    Comments (-1)
  • Quarter 4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/2/2021

    Recent Activities:
    ■ Design committee comprised of District and School leadership, and community members met regularly
    ■ Land Use Application Submitted to City


    Upcoming Activities:
    ■ Design committee comprised of District and School leadership, and community members meet regularly
    ■ Construction Document Design Phase complete early February 2021
    ■ Project out to bid February 2021

    Stadium Lansdcape and path rendering

    Comments (-1)
  • Quarter 3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/28/2020

    Recent Activities:

    • Design committee comprised of District and School leadership, and community members met regularly
    • Design presented at Community Meetings July 15, 21 and 30, 2020
    • Design Development phase of design complete
    • Land Use Application Submitted to City

    Upcoming Activities:

    • Design committee comprised of District and School leadership
    Comments (-1)