Recent Activities:
■ Bus loop storm drain installation complete and opened on time for school
■ Concrete stadium step installation complete, plaza work began in September
■ New stadium seating was installed on the north side of the field
■ Stadium field lighting was completed in September
■ Working on contracting for a new fire alarm system for the stadium


Upcoming Activities:
■ Stadium steel roof beams and columns arriving for install in October
■ Parking lot asphalt scheduled for mid November
■ Parking lot completion scheduled for early December
■ New audio-visual system to be installed