•  West Linn High School '700' Building Renovation
  • District Project Manager: Bob Teters 503-673-7991 

    Contractor: Corp Inc.Construction 
  • WLHS 700 Building Update

    Posted by Amy Berger at 4/20/2017

    Recent Activities:

    • The project is substantially complete and the building is being used by the high school
    • Unforseen conditions during construction extended the construction duration into February
    • Painting building exterior complete
    • Windows and doors complete
    • Interior finishes completed

    Upcoming Activities:

    • The project is in closeout, minor outstanding scope to be completed over the coming months
    Comments (-1)
  • WLHS 700 Building Update

    Posted by Amy Berger at 1/20/2017

    Recent Activities:

    • Unforseen conditions during construction have extended the construction duration to the end of January
    • Roof installation
    • Painting building exterior
    • Windows and doors underway
    • Interior framing underway
    • Mechanical, electrical and plumbing underway
    • Interior finishes underway

    Upcoming Activities:

    • All scope scheduled to be complete by the end of January
    Comments (-1)
  • WLHS 700 Building Update

    Posted by Amy Berger at 10/12/2016

    Recent Activities:

    • Unforseen conditions during construction have extended the construction duration to the end of the academic semester in January.
    • Bus lane complete
    • Concrete sidewalks and ramps complete
    • Landscaping and irrigation began

    Upcoming Activities:

    • Roof installation
    • Painting building exterior
    • Window and doors
    • Interior framing
    • Mechanical, electrical and plumbing
    • Finishes
    Comments (-1)
  • WLHS 700 Building Update

    Posted by Amy Berger at 7/28/2016

    WLHS 700 Building Renovation

    Recent Activities:

    • The contract was awarded to Corp Inc. and the work has begun on site.
    • Sitework demolition is complete.
    • Abatement and selective building demolition is nearing completion.
    • Underground utilities are nearing completion and footings and foundations are underway.

    Upcoming Activities:

    • Site construction will be substantially complete before start of school as planned.
    • Building renovation will begin in late summer and continue through the fall as planned.
    Comments (-1)
  • WLHS 700 Building Activity

    Posted by Amy Berger at 4/20/2016

    West Linn High School 700 Building Renovation

    Recent Activities:

    • The Construction Document estimate showed a marked increase in the anticipated cost of construction based on current market conditions and escalation. Scope, including a new roof was added due to significant structural upgrades that will cause major modifications to the existing roof.
    • The building permit application was submitted to the City of West Linn and the District has received approval for the project.
    • The project was publically bid and 4 bids were received. Two additive alternates were recommended for approval including additional cabinetry and the replacement of existing windows. The low bid was received from Corp Inc. Construction in the amount of $2,527,000.00. The low bid is within current funding. The School Board authorized staff to execute a contract for construction.

    Upcoming Activities:

    • The contractor will begin pre-mobilization activities in preparation for the start of construction in June.

    The project Manager is Bob Teters, tetersb@wlwv.k12.or.us or 503-673-7991

    Comments (-1)
  • 700 Building Project Description & Status

    Posted by Amy Berger at 10/21/2015

    The project site is located at West Linn High School, situated as a separate building on the site. The 700 building was originally constructed in the 1960's as a technical education suite and included spaces for wood working, metal fabrication, and engine repair. Over the years the building has been used for various programs and the aging building requires renovation. The remodeled spaces will be designed to maximize versatility and will be able to accommodate a diverse range of the educational programs including art, environmental science and STEM robotics.

    Design Features Include:

    • Approx 1,100 Square Foot building addition
    • 7 Classrooms
    • Improved ADA accessibility
    • Large storage spaces

    The project is currently in Design Development and will be going out to bid in the Spring with completion Winter 2016.

    Comments (-1)