• Concrete Pour Project Update

    Posted by West Linn - Wilsonville School District on 4/29/2022

    On Wednesday, April 27, the first concrete pour was conducted at the New Athey Creek Middle School Bond Project. The pour consisted of building footings closest to Dollar Street, which will become the back walls of the gym. The City conducted their first building inspections prior to the pour, and Special Inspectors were on site during the installation to take samples of the concrete. The next concrete pour will occur next week as the Contractor continues to form the footings through the first two sectors of the building.

    For more information on the project please visit the bond website. If you have specific questions, please contact Project Manager, Angela Caffrey, via email or phone.

    Angela Caffrey
    caffreya@wlwv.k12.or.us
    503-673-7315 ext 4975

    Concrete Pour

    Comments (-1)
  • 2022 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/28/2022

    Haul Road

    Recent Activities:
    ■ Construction commenced in January working on site clearing and access
    ■ Building and Site permits have been approved by the City of West Linn
    ■ The design team has been working on how to best utilize the lumber that was retained in December
    ■ The district worked with the contractor to retain trees for use in the building entry design
    ■ The contractor installed the main construction access road off Willamette Falls Drive
    ■ Soil has been organized on site to allow it to be reused
    ■ Cement treatment of the soil occurred in March. These treatmens condition the soil to be utilized below the building foundation
    ■ Public improvement drawings were submitted to the City of West Linn in February
    ■ The appeal to the Land Use Board of Appeals was denied on all points. If not appealed, the decision will be final April 18
    ■ Athey Creek staff was presented with the new school design


    Upcoming Activities:
    ■ Cutting of grades will being in April which will define the building foundations
    ■ Procurement of long lead items continues
    ■ Review of the furniture order for the building will continue

    Comments (-1)
  • Project Update March 14, 2022

    Posted by West Linn - Wilsonville School District on 3/14/2022
    • The General Contractor mobilized to the site in January. General site clearing occurred in January, allowing for general excavation.
    • The excavation to lower the site is underway.
    • A temporary road off Willamette Falls Drive has been built to allow major construction traffic access and keep larger vehicles off Dollar Street as much as possible.
    • A secondary access road has been built off Dollar Street, but the primary construction vehicle access is off Willamette Falls drive.
    • The Contractor is preparing a new staging and onsite parking area and will reduce contractor parking along the street.
    • The construction hours are required to align with the City Noise Ordinance. The times noted are in the City Municipal Code.
    • For any questions or concerns about the project, please contact the District’s Project Manager, Angela Caffrey 503-673-7315 ext. 4975

    Site work

    Comments (-1)
  • 2021 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/21/2022

    Recent Activities:
    ■ City Council confirmed the Planning Commissions approval and issued a notice of Final Decision
    ■ The project has been appealed to LUBA (Land Use Board of Appeals)
    ■ Harvesting of the overgrown Christmas tree farm occurred in early December
    ■ Harvested trees have been sold to local mills for a variety of purposes, including milled lumber and pulp
    ■ The district has been meeting to determine best ways to repurpose harvested trees from the site in the project
    ■ The City of West Linn has completed review for the Building Permit
    ■ DEQ approved the 1200-C Erosion Control Permit
    ■ General contractor bids were received. Emerick Construction was awarded the project with all alternates
    ■ Continued collaboration with the City of West Linn for the right of way work along Willamette Falls Drive
    ■ Furniture layouts and design meetings continue


    Upcoming Activities:
    ■ Public Improvement drawings will be submitted to the City in February 2022
    ■ Procurement of long lead items will be addressed with the general contractor
    ■ The contractor will be fully mobilized and on site in Feb/March 2022
    ■ The district submits documentation for the LUBA appeal

    Comments (-1)
  • Fencing Implementation At Dollar Street

    Posted by West Linn - Wilsonville School District on 1/18/2022

    The General Contractor, Emerick Construction Co., has mobilized to the Dollar Street site for the New Athey Creek Middle School.  Installation of construction/safety fencing began on Monday, Jan. 17, and equipment is onsite to perform the initial clearing.   


    The District worked with a firm to harvest the trees from the Christmas Tree area in December. Some of the timber has been retained and will be incorporated into the design for reuse in the school.  

    The permit with the DEQ is in place, as well as the Erosion Control permit with the City, to allow for tree stump removal. Silt fencing and other erosion control measures have been installed with further measures being implemented as the areas of grading increase. The contractor will be bringing a temporary trailer on site today, Jan. 18, until the larger mobile Construction office arrives in the coming weeks.

    For more information on the project please visit the bond website. If you have specific questions, please contact the Project Manager via email or phone.
     
    Angela Caffrey
    caffreya@wlwv.k12.or.us
    503-673-7315  ext 4975
    Comments (-1)
  • Site Work Begins Nov. 29

    Posted by West Linn-Wilsonville on 11/29/2021 7:00:00 AM

    The community will begin to see activity at the Dollar Street property today (Nov. 29) in preparation for the construction of the new Athey Creek Middle School. The district has partnered with a firm for the harvesting of trees for reuse. Applicable permits have been obtained, and the work has been discussed with appropriate agencies. 

    It is important that the community heed the warning signs and flaggers and maintain distance from the property throughout the work. 

    To learn more about upcoming work on the property, including the district’s planning for preservation of natural resources on the property, please visit the bond website.

    Questions can be addressed to the Office of Capital Construction at 503-673-7315 ext 4975. 

    Comments (-1)
  • Preparation for Project Work Begins Soon

    Posted by West Linn-Wilsonville on 11/19/2021 4:00:00 PM

    Soon, activity will start for the new Athey Creek Middle School located at the district-owned Dollar Street property in the Willamette Neighborhood of West Linn. 

    These site preparations are part of the planning and construction process and begin with clearing portions of the land in preparation for a school building.  

    Planning for Preservation of Natural Resources on the Property
    The school district has carefully and intentionally planned for preservation of natural resources wherever possible in the site and building design of this new middle school project. These areas will be periodically inspected by a certified arborist, wetland consultant, soils engineer and civil engineer over the course of the project and they will make recommendations in support of this preservation as needed.

    Our priority is to maintain select trees in the current landscape while incorporating natural elements that neighbors expressed interest in during the community engagement process. 

    We want our families and community members to know that the site will look different as we prepare to break ground on the new school, and we are working thoughtfully with each area of the site to enhance or preserve the area wherever we can.  Here are more specifics of our plan:

    Site Background and Layout
    The District’s Dollar Street property is roughly 22 acres consisting of a variety of natural resources. The design team and engineers have worked to retain these greenspaces in the design, and to position the new middle school building to be enhanced by the surrounding trees, slopes, and greenery.

    Eastern Site Planning
    The eastern portion of the site has a steep ravine. This ravine will be preserved in its entirety. At the central base of the ravine there is an ephemeral stream that will have enhanced native plantings added within this Water Resource Area (WRA.) Trees will be added across the top of the ravine to increase the buffered area for those in the Arbor Cove neighborhood.

    Western Site Planning
    The far western portion of the site includes a Tualatin River Protection Area which is measured based on its proximity to the River. There will be a new path that will be built with minimal disruption. This new path will maintain connectivity to the path under Fields Bridge which connects to the park. There will also be enhanced tree and shrub plantings added at this location.

    Northern Site Planning
    Many of the perimeter trees along Dollar Street must be removed to accommodate the new street and sidewalks required. However, many new trees and shrubs will be installed in an enhanced buffer zone between the new sidewalk and school site features.

    Southern Site Planning
    Many existing trees will be retained along the southern slope of the property. The increased density from new plantings will meld with the existing landscape in a natural way over time.

    Native Trees and Plants
    The District has prioritized the use of native species in planting material throughout the site. This use of native trees and shrubs has been the basis of the design from the onset and was also a resounding comment heard from the Community during the neighborhood meetings in the planning phase. 

    Repurposing of Existing Trees
    The District is exploring opportunities to repurpose trees that need to be removed to accommodate the building, street improvements, and site amenities. Some potential repurposing ideas include timber benches, live edge planks, and instructional material for student interaction. By bringing the natural resource of wood into the building, trees will find new life within the walls of the school and reflect the greenspace on the exterior. Careful consideration of this valued resource will continue to provide a long-term benefit to the community.

    Follow Along As Project Progress Continues
    The District strives to keep neighbors and all interested patrons aware of ongoing progress with this specific construction project as well as all Capital Bond projects.  Patrons can subscribe to the WLWV-Bond-New-Athey-Creek-At-Dollar ListServ service as well as view the bond website. For project information and other updates related to the 2019 Capital Bond, please visit the bond website.

    Comments (-1)
  • Natural Resources Update

    Posted by West Linn-Wilsonville on 11/4/2021 3:00:00 PM

    The New Athey Creek Middle School at Dollar Street Bond Project continues to progress with construction and site preparation expected to begin in the coming weeks. As part of the ongoing construction process, the District would like to share its vision and planning for the natural resources on and around the property. Planning is incredibly intentional to maintain desired aspects of the current landscape while incorporating natural elements that neighbors expressed interest in during the community engagement process.

    Site Background and Layout:
    The District’s Dollar Street property is roughly 22 acres consisting of a variety of natural resources. The design team and engineers have put forth every effort to retain these greenspaces in the design, and to position the new middle school building to be enhanced by the surrounding trees, slopes, and greenery.

    Eastern Site Planning
    The eastern portion of the site has a steep ravine. This ravine will be preserved in its entirety. At the central base of the ravine there is an ephemeral stream that will have enhanced native plantings added within this Water Resource Area (WRA.) Trees will be added across the top of the ravine to increase the buffered area for those in the Arbor Cove neighborhood.

    Western Site Planning
    The far western portion of the site includes a Tualatin River Protection Area which is measured based on its proximity to the River. There will be a new path that will be built with minimal disruption. This new path will maintain connectivity to the path under Fields Bridge which connects to the park. There will also be enhanced tree and shrub plantings added at this location.

    The District has prioritized the use of native species in all planting material. This use of native trees and shrubs has been the basis of the design from the onset and was also a resounding comment heard from the Community during the neighborhood meetings in the planning phase. The new landscape buffers along Dollar Street, trees, and shrubs in the new courtyard, and all plantings surrounding the track and parking areas will also prioritize native plantings. This will ensure that the Pacific Northwest feel, and natural beauty of the property is retained.

    Southern Site Planning
    Many existing trees will be retained along the southern slope of the property. The increased density from new plantings will meld with the existing landscape in a natural way over time.

    Repurposing of Existing Trees
    The District is exploring opportunities to repurpose trees that need to be removed to accommodate the building, street improvements, and site amenities. Some potential repurposing ideas include timber benches, live edge planks, and instructional material for student interaction. By bringing the natural resource of wood into the building, trees will find new life within the walls of the school and reflect the greenspace on the exterior. Careful consideration of this valued resource will continue to provide a long-term benefit to the community.

    More Information to Come
    The District will strive to keep neighbors aware of upcoming construction activities. Neighbors are encouraged to look for communication through this ListServ service and the bond website. For project information and other updates related to the 2019 Capital Bond, please visit the bond website.

    Comments (-1)
  • 2021 Quarter 3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/21/2021

    courtyard rendering

    Recent Activities:
    ■ City of West Linn Planning Commission approved the project with conditions in August
    ■ Willamette Neighborhood Association appealed the Planning Commission decision
    ■ Permit drawing set completed in July and submitted to the City of West Linn Building Department
    ■ Advertisement to pre-qualify bidders sent to the DJC, qualifying method approved by the School Board
    ■ Continued collaboration for the City’s portion of the right of way work along Willamette Falls Drive
    ■ Furniture layouts and design meetings continue

    Upcoming Activities:
    ■ Contractor proposals due October 6th, review period October 7-15 and the list of qualified contractors released
    October 15th
    ■ Advertise to bid the project October 20th with bids due December 8th
    ■ City Council Meeting set for October 4th
    ■ Final decision from West Linn City Council meeting

    Arts porch rendering
    New Arts Porch Rendering

    commons rendering from Athey Idol night
    Athey Idol Rendering from upper commons looking down

    Maker porch
    Lower level makerspace porch

    Porch rendering
    Porch Rendering

     

    Comments (-1)
  • NEW ATHEY CREEK MIDDLE SCHOOL ON DOLLAR STREET – PROJECT UPDATE

    Posted by West Linn - Wilsonville School District on 8/19/2021

    Entry Rendering

    Land Use documents were submitted to the City Planning Department in March and the initial Completeness was received on April 16th.  The Land Use process has continued over the summer with the initial hearing, followed by subsequent hearings and findings.  The final hearing was held on August 18th which ended in a vote by the Planning Commission.  The Planning Commissioners voted to approve the application with conditions.

    Updated conceptual renderings of the main entry, as shown above, as well as the bus entry and interior spaces can be found in the project image slideshow as well as here, below.

    The project documents have been completed and submitted to the Building Department for Permit.  The District has received the first round of comments back from the Building Department and is responding.  It is anticipated that the Permitting and Land Use processes will converge in a timely manner to allow Contractor bidding to begin in the fall.

    The District has engaged with a Furnishings Fixtures & Equipment (FF&E) vendor and has begun the process of furniture selection.  These selections are all based on the final interior color palette selections, which were also finalized over the summer.

    The District continues to partner with City of West Linn in developing Street Improvements surrounding the site.  Street improvements will occur on Dollar Street, Willamette Falls Drive, and the newly created Brandon Place Extension.  Final coordination efforts are nearing completion to allow right of way improvements to be submitted to the City in the fall.

    Back entry rendering
    Back side of school conceptual rendering

    Commons Rendering
    Commons Conceptual Rendering

    Library Rendering
    Library conceptual rendering

    Upstairs Rendering
    Upstairs Classrooms/porch conceptual rendering

    Comments (-1)