2023 Q3 Project Updates

Posted by West Linn - Wilsonville School District on 10/31/2023

Recent Activities:
■    Classes began as scheduled August 29th
■    Staff was able to move in a week prior to school and get settled in the building
■    Building mechanical and electrical systems are fully functioning including the kitchen
■    Furniture was installed and is in use
■    The auxiliary gym was opened two weeks into school and the main gym will open at the end of October
■    The main parking lot and staff parking lot are complete with minor areas of planting still ongoing
■    Bus drop off and pick up is functioning as intended
■    A temporary access road was constructed to provide access from Brandon Place to Willamette Falls Drive
■    The playground is fully functional and the turf field is slated to be complete at the end of October

Upcoming Activities:
■    Theater components have had on-going delays throught the industry. The stage is anticipated to be complete in early to mid November
■    Operations training of all building systems to occur in late October
■    Roundabout construction is tentatively planned for early November