- 2019 Capital Bond
- Project Updates
WHS Performing Arts Center
Page Navigation









































-
To receive project updates for the Wilsonville High Performing Arts Center, sign up for the WLWV-Bond-WHS-Performing-Arts-Center ListServ.
-
Wilsonville HS New Performing Arts Center
Posted by West Linn - Wilsonville School District on 7/25/2023Tour the brand-new Performing Arts Center at Wilsonville High School. Check out the massive stage, impressive lighting, and behind the scenes working spaces that will help our students get a jump start on their dreams of turning the passion of theater into a career.
-
2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023Recent Activities:
■ Phase 4 is underway, which includes the Black Box and old theater conversion to CTE spaces
■ Old auditorium in-fill is complete and structural work is underway
■ Theater rigging sytems inspections have been completed
■ Required firewall work is currently underway
■ Electrical rough in has started in teh new CTE spaces
■ Final accoustical treatments have been installed
■ Roof repairs have begun
■ Final site plantings are underwayUpcoming Activities:
■ Mechanical rough-in in the CTE space
■ Stud framing work to begin on the new interior walls for the new CTE and Black Box spaces
■ Installation of exterior building signage
■ Additional mechanical screen wall work
■ Existing exterior wall corrective work
■ Final site work -
Project Updates
Posted by West Linn - Wilsonville School District on 6/6/2023The WHS Auditorium Addition and WHS renovation project has reached another significant milestone: TCO (Temporary Certificate of Occupancy). As such, the school programs have moved into the new space allowing Todd Construction to begin phase 4; the renovation of existing space into the new Black Box theatre and CTE spaces.
The move into the new space provided the additional benefit of hosting three events in the space this last week. This has provided the staff and students the opportunity to start learning the new systems and start the process of performance testing the new performance venue with a “soft open”.
The project team is excited to welcome the public on a larger scale next fall when the entire PAC is anticipated to be completed. Please stay tuned this summer for the Fall Grand Opening celebration announcements
If you have any questions, please contact the Project Manager.
R. Ryan Hendricks
253.307.3687
Thank YOU for supporting the Capital Bond and Local Option to make this work possible.
Be sure to visit the Bond Website to stay informed about projects district-wide.
Capital Bond Coordinator – Amy Berger
www.bond.wlwv.k12.or.us -
Project Updates
Posted by West Linn - Wilsonville School District on 5/22/2023The WHS Auditorium Addition and WHS renovation project has reached a significant milestone. Though the building is still closed as we continue to work on the finishes inside the building, the site fencing is coming down which means that the North and South plazas are now open, the north parking lot is open along with the the new site connector road along the west side of the new addition.
Please take extra caution as everyone is experiencing new site traffic patterns. Please observe all traffic control signage on site and be aware the pedestrian traffic will change due to the additional options on the site.
The project team welcomes you to use the new site facilities and is excited to be getting closer to starting the next and final phase of the project.
If you have any questions, please contact the Project Manager.
R. Ryan Hendricks
253.307.3687
Thank YOU for supporting the Capital Bond and Local Option to make this work possible.
Be sure to visit the Bond Website to stay informed about projects district-wide.
Capital Bond Coordinator – Amy Berger
www.bond.wlwv.k12.or.us -
2023 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/20/2023Recent Activities:
■ Softball field is open and in use
■ Auditorium architectural finishes are nearing completion
■ Final installation theatrical AV and lighting systems is underway
■ Theaterical seating installation is complete
■ Stage rigging is complete
■ Building exterior metal cladding continues
■ Utilities are complete and operationsl
■ Drive loop complete
■ Window installation nearing completion
■ Stage wood floor installation is completeUpcoming Activities:
■ Installation of acoustical treatments final install waiting on manufacturing delays
■ Completion of site plantings to continue
■ Black Box Theater conversion to CTE space to occur over the summer
■ Remedial floor and roof work to occur over the summer -
2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/2023Recent Activities:
- Softball field work including concrete flatwork continues.
- Interior finishes are currently being installed
- Theatrical AV and Lighting systems are currently being installed
- Theatrical seating has arrived and the installation process has begun
- Windows have been installed
- Wood architectural paneling installation has begun in the theater space
- Building exterior metal cladding is over 50% complete
- Concrete floor polishing is in progress
- Door and hardware installation has begun
- North parking lot is complete, finishing work on the drive loop continues
Upcoming Activities:
- Completion of softball field and is expected to be ready for play at the start of the season in February
- Storefront window vestibules installation
- Stage wood floor installation
- Installation of acoustical treatments
- Mechanical, electrical and plumbing equipment startup and commissioning
- Completion of site plantings
- PGE services installation
-
2022 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/26/2022Recent Activities:
■ Stair structures are complete
■ Mechanical, Electrical and Plumbing rough-in is nearing completion
■ Site concrete work is ongoing. North and South plaza work has begun
■ New turf for the softball field has been laid and fence post installation is nearing completion
■ Front entry work has been completed
■ North parking lot is nearing completion
■ Security upgrades to the existing building have been completed
■ Sheetrock installation has begun and roofing work is nearing completionUpcoming Activities:
■ Window framing work to begin
■ AV wiring and device installation
■ Lighting and control installation
■ Wood architectural panellininstallation in the auditorium to begin
■ Building exterior metal cladding installation -
2022 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/22/2022Recent Activities:
■ Exterior brick is over 75% installed
■ Mechanical, Electrical and Plumbing rough-in continues throughout. Inter building connections have begun
■ Framing for the South lobby exterior wall has begun
■ New sewer main relocated and installed
■ Concessions stand re-roof is nearing completion
■ Excavation for the artificial turf softball field has begun
■ Musco light poles and light heads have been installed
Upcoming Activities:
■ Internal stairwell steel
■ Framing of the North lobby
■ Completion of the concrete slabs
■ Site access entry rework at school main entry
■ North parking lot work to begin
■ Security upgrades in existing building to start -
Bond Construction Update: Wilsonville High School Auditorium
Posted by West Linn - Wilsonville School District on 7/19/2022Have you noticed all the construction going on at Wilsonville High School? Check out the latest project update on the new auditorium being built at Wilsonville High School. Work on the project is being designed not only for the school, but also to be used by the entire Wilsonville community.
-
2022 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/28/2022Recent Activities:
■ Main auditorium roof trusses are in place
■ Catwalks are being installed
■ Balcony steel is going in place
■ Weather proofing is being applied to exterior face of the building
■ Exploratory work for mechanical system connection to the new addition is taking place
Upcoming Activities:
■ Exterior brick to be installed
■ Mechanical, electrical and plumbing in the new lobby restrooms
■ Footings for both lobbies to be excavated and poured
■ Installation of sewer main relocation