• 2023 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/25/2024

    Recent Activities:
    ■    Project is substantially complete
    ■    Contractor punch work items being addressed
    ■    Exterior building signage at north entry is complete

    Upcoming Activities: 
    ■    Project closeout
    ■    Installation of exterior building signage on south entry
    ■    Additional mechanical screen wall work

    Comments (-1)
  • WHS Auditorium Dedication

    Posted by West Linn - Wilsonville School District on 11/2/2023

    Join Us for the Dedication of the Wilsonville High School Performing Arts Center

    The entire community is invited to the Wilsonville High School Performing Arts Center Dedication Ceremony on November 13 starting at 7 p.m.; 6880 SW Wilsonville Road.

    The event will include an official ribbon cutting ceremony and student-led tours of the new building.

    WHS Invitation

    Comments (-1)
  • 2023 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/31/2023

    makerspace

    Recent Activities:
    ■    Phase 4, which includes the Black Box and old theater conversion to CTE spaces are nearing completion
    ■    Required firewall work is complete
    ■    The technology hub is being used by the school
    ■    Roof repairs are complete with flashing work nearing completion
    ■    Final site plantings are complete
    ■    Contractor punch work items being addressed

    Upcoming Activities: 
    ■    Contractor punch list items continue
    ■    Installation of exterior building signage
    ■    Additional mechanical screen wall work

    Comments (-1)
  • Wilsonville HS New Performing Arts Center

    Posted by West Linn - Wilsonville School District on 7/25/2023

    Tour the brand-new Performing Arts Center at Wilsonville High School. Check out the massive stage, impressive lighting, and behind the scenes working spaces that will help our students get a jump start on their dreams of turning the passion of theater into a career.

    Comments (-1)
  • 2023 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/20/2023

    Recent Activities:
      Phase 4 is underway, which includes the Black Box and old theater conversion to CTE spaces
        Old auditorium in-fill is complete and structural work is underway
        Theater rigging sytems inspections have been completed
        Required firewall work is currently underway
        Electrical rough in has started in teh new CTE spaces
        Final accoustical treatments have been installed
        Roof repairs have begun
        Final site plantings are underway

    Upcoming Activities:
        Mechanical rough-in in the CTE space
        Stud framing work to begin on the new interior walls for the new CTE and Black Box spaces
        Installation of exterior building signage
        Additional mechanical screen wall work
        Existing exterior wall corrective work
        Final site work

    Exterior view

    Comments (-1)
  • Project Updates

    Posted by West Linn - Wilsonville School District on 6/6/2023

    WHS Auditorium Interior

    The WHS Auditorium Addition and WHS renovation project has reached another significant milestone: TCO (Temporary Certificate of Occupancy).  As such, the school programs have moved into the new space allowing Todd Construction to begin phase 4; the renovation of existing space into the new Black Box theatre and CTE spaces. 

    The move into the new space provided the additional benefit of hosting three events in the space this last week. This has provided the staff and students the opportunity to start learning the new systems and start the process of performance testing the new performance venue with a “soft open”.   

    The project team is excited to welcome the public on a larger scale next fall when the entire PAC is anticipated to be completed.  Please stay tuned this summer for the Fall Grand Opening celebration announcements

    If you have any questions, please contact the Project Manager.

     

    R. Ryan Hendricks

    hendricr@wlwv.k12.or.us

    253.307.3687

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Bond Coordinator – Amy Berger

    www.bond.wlwv.k12.or.us

    Comments (-1)
  • Project Updates

    Posted by West Linn - Wilsonville School District on 5/22/2023

    WHS Exterior

    The WHS Auditorium Addition and WHS renovation project has reached a significant milestone. Though the building is still closed as we continue to work on the finishes inside the building, the site fencing is coming down which means that the North and South plazas are now open, the north parking lot is open along with the the new site connector road along the west side of the new addition.

    Please take extra caution as everyone is experiencing new site traffic patterns. Please observe all traffic control signage on site and be aware the pedestrian traffic will change due to the additional options on the site.

    The project team welcomes you to use the new site facilities and is excited to be getting closer to starting the next and final phase of the project.

    If you have any questions, please contact the Project Manager.

     

    R. Ryan Hendricks

    hendricr@WLWV.k12.or.us

    253.307.3687

     

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Bond Coordinator – Amy Berger

    www.bond.wlwv.k12.or.us

     

    Comments (-1)
  • 2023 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/20/2023

    WHS Auditorium Seating

    Recent Activities:
      Softball field is open and in use
        Auditorium architectural finishes are nearing completion
        Final installation theatrical AV and lighting systems is underway
        Theaterical seating installation is complete
        Stage rigging is complete
        Building exterior metal cladding continues
        Utilities are complete and operationsl
        Drive loop complete
        Window installation nearing completion
        Stage wood floor installation is complete

    Upcoming Activities:
        Installation of acoustical treatments final install waiting on manufacturing delays
        Completion of site plantings to continue
        Black Box Theater conversion to CTE space to occur over the summer
        Remedial floor and roof work to occur over the summer

    Comments (-1)
  • 2022 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/3/2023

    WHS Entry

    Recent Activities:

    • Softball field work including concrete flatwork continues.
    • Interior finishes are currently being installed
    • Theatrical AV and Lighting systems are currently being installed
    • Theatrical seating has arrived and the installation process has begun
    • Windows have been installed
    • Wood architectural paneling installation has begun in the theater space
    • Building exterior metal cladding is over 50% complete
    • Concrete floor polishing is in progress
    • Door and hardware installation has begun
    • North parking lot is complete, finishing work on the drive loop continues

     

    Upcoming Activities:

    • Completion of softball field and is expected to be ready for play at the start of the season in February
    • Storefront window vestibules installation
    • Stage wood floor installation
    • Installation of acoustical treatments
    • Mechanical, electrical and plumbing equipment startup and commissioning
    • Completion of site plantings
    • PGE services installation
    Comments (-1)
  • 2022 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/26/2022

    high school north entry exterior

    Recent Activities:
      Stair structures are complete
      Mechanical, Electrical and Plumbing rough-in is nearing completion
      Site concrete work is ongoing. North and South plaza work has begun
      New turf for the softball field has been laid and fence post installation is nearing completion
      Front entry work has been completed
      North parking lot is nearing completion
      Security upgrades to the existing building have been completed
      Sheetrock installation has begun and roofing work is nearing completion

    Upcoming Activities:
      Window framing work to begin
      AV wiring and device installation
      Lighting and control installation
      Wood architectural panellininstallation in the auditorium to begin
      Building exterior metal cladding installation

    Comments (-1)