2023 Q1 Project Updates

Posted by West Linn - Wilsonville School District on 4/20/2023

WHS Auditorium Seating

Recent Activities:
  Softball field is open and in use
    Auditorium architectural finishes are nearing completion
    Final installation theatrical AV and lighting systems is underway
    Theaterical seating installation is complete
    Stage rigging is complete
    Building exterior metal cladding continues
    Utilities are complete and operationsl
    Drive loop complete
    Window installation nearing completion
    Stage wood floor installation is complete

Upcoming Activities:
    Installation of acoustical treatments final install waiting on manufacturing delays
    Completion of site plantings to continue
    Black Box Theater conversion to CTE space to occur over the summer
    Remedial floor and roof work to occur over the summer