2022 Q4 Project Updates

Posted by West Linn - Wilsonville School District on 2/3/2023

WHS Entry

Recent Activities:

  • Softball field work including concrete flatwork continues.
  • Interior finishes are currently being installed
  • Theatrical AV and Lighting systems are currently being installed
  • Theatrical seating has arrived and the installation process has begun
  • Windows have been installed
  • Wood architectural paneling installation has begun in the theater space
  • Building exterior metal cladding is over 50% complete
  • Concrete floor polishing is in progress
  • Door and hardware installation has begun
  • North parking lot is complete, finishing work on the drive loop continues

 

Upcoming Activities:

  • Completion of softball field and is expected to be ready for play at the start of the season in February
  • Storefront window vestibules installation
  • Stage wood floor installation
  • Installation of acoustical treatments
  • Mechanical, electrical and plumbing equipment startup and commissioning
  • Completion of site plantings
  • PGE services installation