2024 Q1 Project Updates

Posted by West Linn - Wilsonville School District on 4/23/2024

Drone image of roundabout

Recent Activities:
■    The turf field and track are being used by the school and community for sports activities and practices
■    Landscaping is complete and is under warranty for one year. Irrigation is complete
■    The roundabout at Fields Bridge Park is nearing completion
■    Public street improvements (grading, retaining walls, sidewalks, bike lanes, crosswalks, pedestrian flashers, street lighting and storm drainage) has commenced

Upcoming Activities:
■    Track completion to occur summer 2024
■    Public street improvements continue through summer 2024
■    Roundabout work continues through April 2024
■    The temporary access road will be closed with the roundabout opens
■    City of West Linn youth baseball is utilizing Athey Creek parking lots during construction after school and on weekends