2023 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 7/20/2023

Parking Lot View

Recent Activies:
     Permanent power, water and networking are all up and running in the building
     Interior finishes are underway, including acoustic ceiling tiles, light fixtures, painting, tile and casework
     Large kitchen equipment is being installed, including hood, walk in cooler and walk in freezer
     Theater equipment is being installed
     Elevator installation is complete
     Interior doors are being installed
     All Athey items have been moved out of the old building and into trailers until ready to go into the new space
     Final paving was completed on Dollar Street and staff parking lot
     The lower visitor parking lot and new driveway from Brandon Place were installed along with all sidewalks and striping. Parking lot islands are being irrigated and prepped for planting.
     Brandon Place is paved
     Exterior windows are nearly completed with the exception of the entry vestibules
     Solar array panels are installed on the upper level bus canopies
     Exterior light poles have been installed
     Both generators are installed and will begin testing
     The roof is complete and all but one rooftop unit is placed, with completion in late July
     Landscaping has begun and will be ongoing throughout the summer months
     Fence installation has begun
     The concessions building is being constructed

Upcoming Activities
     Gym flooring is scheduled to start in July
     HVAC installation is expected to be complete at the end of July with testing to follow in August
     Interior glazing will begin in July
     The track and field are being prepared for installation
     The playground equipment will be installed in the coming months
     Reconstruction of the West entry to Fields Bridge Park and construction of the roundabout is pending City of West Linn permitting
     Furniture arrives on site July 17th and will be installed over a three-week period
     Movers will bring Athey Creek staff stored items to the site the first week of August
     Meeting with the City of West Linn to confirm temporary occupancy requirements
     Meeting with TVF&R to outline occupancy requirements
     Temporary entry constructed from Willamette Falls Drive