2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023
Recent Activies:
■ Permanent power, water and networking are all up and running in the building
■ Interior finishes are underway, including acoustic ceiling tiles, light fixtures, painting, tile and casework
■ Large kitchen equipment is being installed, including hood, walk in cooler and walk in freezer
■ Theater equipment is being installed
■ Elevator installation is complete
■ Interior doors are being installed
■ All Athey items have been moved out of the old building and into trailers until ready to go into the new space
■ Final paving was completed on Dollar Street and staff parking lot
■ The lower visitor parking lot and new driveway from Brandon Place were installed along with all sidewalks and striping. Parking lot islands are being irrigated and prepped for planting.
■ Brandon Place is paved
■ Exterior windows are nearly completed with the exception of the entry vestibules
■ Solar array panels are installed on the upper level bus canopies
■ Exterior light poles have been installed
■ Both generators are installed and will begin testing
■ The roof is complete and all but one rooftop unit is placed, with completion in late July
■ Landscaping has begun and will be ongoing throughout the summer months
■ Fence installation has begun
■ The concessions building is being constructed
Upcoming Activities
■ Gym flooring is scheduled to start in July
■ HVAC installation is expected to be complete at the end of July with testing to follow in August
■ Interior glazing will begin in July
■ The track and field are being prepared for installation
■ The playground equipment will be installed in the coming months
■ Reconstruction of the West entry to Fields Bridge Park and construction of the roundabout is pending City of West Linn permitting
■ Furniture arrives on site July 17th and will be installed over a three-week period
■ Movers will bring Athey Creek staff stored items to the site the first week of August
■ Meeting with the City of West Linn to confirm temporary occupancy requirements
■ Meeting with TVF&R to outline occupancy requirements
■ Temporary entry constructed from Willamette Falls Drive
Recent
By Month
- November 2024
- July 2024
- April 2024
- January 2024
- October 2023
- July 2023
- April 2023
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- July 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- August 2021
- April 2021
- March 2021
- February 2021
- January 2021
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- February 2020