Posted by West Linn - Wilsonville School District on 4/28/2022
Recent Activities:
■ Temporary Occupancy was received from the City of West Linn in March
■ Concrete layout in the upper plaza continues and curved walls have been poured
■ Landscape installation is in progress
■ Drainage has been incorporated into the parking lot and paving is being scheduled
■ New Audio Visual system is installed and press boxes are being used
■ Games are being played on the field and the stadium seating is being used
Upcoming Activities:
■ Paving of the new parking lot is scheduled for April
■ The connection of the new walking path to the crosswalk of the upper north lot continues
■ Handrails, landscaping and items for final occupancy are in progress