2021 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 8/4/2021

Recent Activities:
■ Notice to proceed issued to contractor in April
■ Contractor began early site mobilization late April
■ Parking lot, plaza and stadium seating work began
■ Storm drain work in the bus loop to began re-route the storm line
■ Building permit received late June
■ Work fully underway after release of school for the summer late June

Upcoming Activities:
■ Work on the corner of West A Street and Skyline scheduled for completion in July
■ Added work in the bus loop scheduled for completion prior to start of school
■ Stadium seating area scheduled for completion end of September
■ Completion of the Parking lot and Plaza scheduled for October

Ariel photo of construction