2024 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/31/2024Recent Activities:
■ Brisband Street has been opened to allow public traffic. Sherman Drive has been closed to facilitate road improvement work
■ Classroom and office casework, such as shelving, cubbies, and sinks are being installed
■ Drywall has been installed in most of the building, including classrooms, library and many office and storage areas
■ Installation of light fixtures and the ceiling grid are in progress in offices and classrooms
■ Installation of plumbing equipment, including boilers, water heaters and pumps have occurred
■ Brick and the fiber cement siding have been installed around the majority of the building’s exterior
■ The entry and solar array canopy framing have been completed. Installation of the flooring, light fixtures, solar panels and exterior finishes to followUpcoming Activities:
■ Site work is expected to begin at both the main courtyard and the playground. Placement of boulders and log benches to occur first, followed by concrete site walls
■ The utility yard concrete slab and housekeeping pads will be poured in preparation for the arrival of the trash compactor, generators, and switchgear equipment
■ More interior finishes to begin installation, including ceramic tile in the restrooms and ceilings in hallways -
Frog Pond Primary Update
Posted by West Linn - Wilsonville School District on 7/30/2024 -
2024 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/23/2024Recent Activities:
■ The exterior framing of the building is complete
■ Installation of exterior finishes such as, brick, fiber cement siding, waterproofing products and windows continues to progress around the perimeter of the building
■ Mechanical, electrical and plumbing work continues to follow framing throughout the building
■ Underground utilities continue to be installed throughout the site and will continue as construction progresses. Utility connections along Sherman Drive have been completed
■ Completion of many of the classroom asphalt roofs have allowed for installation of drywall, door drains and casework
■ The sanitary sewer and storm lines have been installed along Brisdband Street. Installation of the public water line has begunUpcoming Activities:
■ Construction of stormwater planters along Brisband Street to begin in the near future
■ Coordination continues to occur between the School District and the Boeckman Road Corridor Improvements Project
■ Construction of the exterior canopies around the building to begin soon
■ Completion of the public water line -
2023 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 1/25/2024Recent Activities:
■ Framing continues with a substantial portion of the building largely complete. The entry vestibule, library, offices and many classrooms are fully framed
■ Underground utility installation is underway with utility connections along Sherman Drive complete
■ Installation of exterior finishes such as brick, waterproofing and windows has begun
■ The entirety of the building’s concrete floor slab is complete
■ Plumbing, HVAC and electrical rough-ins have started in the classrooms and offices
■ Installation of roofing is underwayUpcoming Activities:
■ Storm and sewer piping installation along the Brisband Street connection is expected to begin late January
■ Remaining framing for gym, kitchen, music room and multi-purpose room
■ Installation of plumbing, HVAC and electrial to follow remaining framing work
■ Coordination between the City of Wilsonville and the District continues for the construction of the school and the City’s work on the Boeckman Road Corridor Improvements project -
2023 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/31/2023Recent Activities:
■ The existing house and barns on the property were demolished and removed from the site
■ Significant site grading occurred and the existing wells on site were decommissioned
■ Erosion control and tree protection measures, such as hydroseeind, silt fences and sediment ponds were imple-mented throughout the site
■ Uderground utilities have been installed and the buildings footings have been poured
■ The first classroom sections framing has begunUpcoming Activities:
■ Work has begun on the street improvements for both Sherman Drive and Brisband Street. Connections for utili-ties to be completed in the coming weeks
■ The installation of concrete floor slab, as well as wood-framed structure continues
■ Coordination between the City of Wilsonville and the District continues for the construction of the school and the City’s work on the Boeckman Road Corridor Improvements project -
2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023Recent Activies:
■ Board approved contract with alternates
■ Contract executed
■ Abatement of existing buildings complete
■ Contractor mobilized to the siteUpcoming Activities:
■ Continued coordination between the City of Wilsonville and the District for the school work and City's work on the Boeckman Road Coordinator Improvements project
■ Completion of erosion control and tree protection measures
■ Start of construction -
Community Celebrates Groundbreaking for New Primary School
Posted by West Linn - Wilsonville School District on 6/14/2023School Board Directors, City Leaders, and School District Staff officially broke ground on the New Primary School at Frog Pond on June 12.
The new primary school is part of the 2019 Capital Bond to address enrollment growth as the Frog Pond neighborhood builds out. The 350-student starter school will open in 2025-26.
Interested community members can take a virtual tour of the new school by clicking here.
-
2023 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/20/2023Recent Activities:
■ The project was granted land use approval at the City of Wilsonville Development Review Board April 10th
■ An abatement package was bid and a contract has been executed for abatement of the existing house on the property.
■ Project bids were received on April 11thUpcoming Activities:
■ The project will go to the school board on April 17th for contractor approval.
■ Continued coordination between the City of Wilsonvillea and the district for the school work and the city's work on the Boeckman Road Corridor Improvements project.
■ Abatement of the existing house to occur in May
■ Construction start is anticipated in June -
2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/2023Recent Activities:
- New School Construction Development phase continues
- 60% design set being reviewed by the district
- After consideration of the previous quarters and Post COVID-19 construction material availability/lead times assessment, the decision was made to extend the construction schedule and therefore push the opening of the school to fall 2025
- Value engineering continues in efforts to bring cost within budget
- The project was submitted to the City of Wilsonville for Land Use approval in December
- General contractor pre-qualification proposals were received in December. An evaluation committee has reviewed and will release the qualified bidders list in January 2023
Upcoming Activities:
- New School Construction Document Design phase meetings with district stakeholders and consultants continue
- Continued work with the City of Wilsonville throughout Land Use to achieve approval
- Project goes out to bid in February for pre-qualified bidders
- Construction documents will be completed and submitted to the City of Wilsonville for the building permit review and approval
-
Activity at Frog Pond Site
Posted by West Linn - Wilsonville School District on 1/19/2023The District is working with Tualatin Valley Fire and Rescue and the Clackamas County Sheriff’s Office to facilitate training at the existing house on the future site for the new primary school at 7151 SW Boeckman Rd. This house will eventually be demolished and the District is excited to offer this now empty facility for training in which firefighters and police will get to learn how to use new equipment for search and rescue and K9 training. This exercise will take place over the next few months. The community will see multiple fire engine’s and other emergency vehicles on the property and possibly “fake smoke” that they will use to mimic search and rescue efforts in smoke from a fire. These exercises will begin next week, January 23rd.
If you have any questions, please contact the Project Manager:
Nick Reiner
503-673-7976
Thank YOU for supporting the Capital Bond and Local Option to make this work possible.
Be sure to visit the Bond Website to stay informed about projects district-wide.
Bond Coordinator – Amy Berger