• Primary School at Frog Pond Open House Scheduled for Aug. 23

    Posted by West Linn-Wilsonville on 8/12/2022 2:00:00 PM

    The City of Wilsonville and the West Linn-Wilsonville School District will hold an open-house style meeting on Tuesday, Aug. 23 from 6:00-8:00pm at Meridian Creek Middle School. The purpose of the Open House is to provide information, answer questions, and receive feedback on three significant projects in Wilsonville.

    City and District staff will be present to discuss the New Primary School, Boeckman Road Corridor Improvements, and Frog Pond East and South. Community members unable to attend the event in-person will be able to view presentation materials online. All community members are encouraged participate in online surveys to ask questions and provide feedback on each project. Links to the materials and surveys will be made available at the event.

    New Primary School: Project Contact – Brooke Besheone (besheonb@wlwv.k12.or.us)

    Funded through the 2019 Capital Bond Program and expected to open in the fall of 2024, the new 350 student starter primary school is planned for District-owned property along Boeckman Road. The design will contemplate a future expansion to serve 550 students. The first open house and community survey held in May of this year resulted in roughly 50 responses. A frequently asked questions document has been posted to the project website at the following web address:

    https://www.wlwv.k12.or.us/Page/16718

    The District and design team have worked to incorporate the community feedback received through that process and are eager to present the site plans and conceptual renderings of the school and receive feedback. The District expects to submit documents for a land-use permit to the City of Wilsonville in the weeks following the event. While the District hopes to receive all questions and comments directly, the City permit process also includes opportunities for public input.

    The District has not determined the attendance boundary, and no boundary related information will be available at the event. A public process regarding the attendance boundary is expected in 2023.

    Boeckman Road Corridor Improvement Project: Project Contact – Andrew Barrett (abarrett@ci.wilsonville.or.us)

    The Boeckman Road Corridor Improvement Project completes several upgrades on Boeckman Rd., between Canyon Rd. and Stafford Rd., to bring the road to urban standards and accommodate the growth of Frog Pond neighborhoods. Most notably, the project includes the construction of a new bridge over the “Boeckman Dip” to flatten the steep roadway to increase safety and mobility for drivers, cyclists, and pedestrians, and to restore fish and wildlife passage.

    Bridge construction includes removal of existing culverts, stream restoration, and completion of a section of the Boeckman Creek Regional Trail. Additional work is being completed to add landscaping, lighting, and separated bicycle and pedestrian facilities; and to improve the Boeckman/Canyon Creek intersection.  The project also provides pedestrian crossings, storm drainage upgrades, and a new sanitary sewer trunk.

    Design is now underway. When bridge construction begins in summer 2023, Boeckman Rd. will be closed to all traffic between Canyon Creek and Sherman Drive for up to 15 months. This and other construction impacts will be noticed by the City before construction begins. 

    The City welcomes the opportunity to discuss all aspects of the project with the community at this event. Learn more at: ci.wilsonville.or.us/Boeckman.

    Frog Pond East and South: Project Contact – Dan Pauly (pauly@ci.wilsonville.or.us)

    The Frog Pond East and South Master Plan has been an active conversation in the community since 2017. These master plans contemplate the needs of an expanding community, including the types and locations of the homes, parks, open spaces, streets, trails and neighborhood amenities for the next 10-20 years. Funding for the master plan has been provided through a grant with Metro. The City has worked to engage with the community throughout the process and has two active surveys available online. In addition to this open house event, the project team will be available at Popsicles in the Park on August 9 and the Community Block Party August 25. The project team will be present to answer questions and receive feedback from the community regarding design elements (including sidewalks, bike paths, street crossings, and parks) as well as housing history. More information about the surveys and those other events is available on the City website at the following address: https://www.letstalkwilsonville.com/frogpond.

    Frog Pond West Community Park: Project Contact - Dustin Schull (dschull@ci.wilsonville.or.us)

    The City is excited to begin a collaboration with community members to develop Wilsonville’s next great park. This new park, to be built in Wilsonville's new Frog Pond West neighborhood, is about 3 acres in size.  Funding is to come from Metro's Local Share program and the City. Parks & Recreation staff is inviting community members to take a short survey that is to help guide park planners in the design of this new park. By sharing your thoughts, you are helping to ensure that Wilsonville continues to develop first-rate amenities that match the community's needs. Take the survey in English or in Spanish at: https://www.letstalkwilsonville.com/frog-pond-west-community-park.

    Comments (-1)
  • Save the Date!

    Posted by West Linn - Wilsonville School District on 8/11/2022

    Front Exterior Rendering

    Save the Date! The District will be hosting a community open house to discuss the New Wilsonville Primary School that will be built on District property at 7151 SW Boeckman Road. The City of Wilsonville will also be present to share information about their own projects in the area. More information about this event will be forthcoming.

    Date: August 23rd, 2022 @ Meridian Creek Middle School; 6:00pm – 8:00pm

     

    If you have any questions, please contact the Project Manager:

    Brooke Besheone

    besheonb@wlwv.k12.or.us

    503-673-7990

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Construction Office Manager – Amy Berger

    Comments (-1)
  • 2022 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/22/2022

    Recent Activities:
    ■ New School Schematic Design phase began in mid March and wrapped up in early June. Design Development
    Design phase started Mid June and continues into September
    ■ Geotechnical report was received with no significant concerns
    ■ Meetings with district staff occurring to ensure design is developed with long term functionality in mind
    ■ A preliminary cost estimate has been received, value engineering efforts will continue to reduce cost
    ■ A community Open House was held in early April
    ■ The new storage building is open and being used by district staff


    Upcoming Activities:
    ■ New School Design Development phase meetings continue with district stakeholders and consultants
    ■ A second community Open House to be held late this summer

    Comments (-1)
  • New Primary School FAQ Document

    Posted by West Linn - Wilsonville School District on 7/7/2022

    Good afternoon WLWV families,

    This Spring, the District held a community open house to discuss the New Wilsonville Primary School that will be built on District property at 7151 SW Boeckman Road in the Frog Pond Neighborhood. Through this open house and the Community Survey, the district has generated a Frequently Asked Questions document that is posted on the project website. This FAQ can be found here. Please keep in mind this is a living document with the intent to add to it as more questions arise.

    The district will have another Open House at a date later this summer. Be on the lookout for that information in the coming weeks. 

    The district appreciates hearing from the community with any hopes or concerns that people might have. The feedback received is being considered as early concepts are being developed.

    To view the FAQ, follow this link.

    There is no boundary map for the new primary school. The district expects to consider primary school boundaries in 2023.

     

    If you have any questions, please contact the Project Manager:

    Brooke Besheone

    besheonb@wlwv.k12.or.us

    503-673-7990

    Thank YOU for supporting the Capital Bond and Local Option to make this work possible.

    Be sure to visit the Bond Website to stay informed about projects district-wide.

    Capital Bond Coordinator – Amy Berger

    Comments (-1)
  • Community Survey Link

    Posted by West Linn - Wilsonville School District on 5/10/2022

    Last week the District held a community open house to discuss the New Wilsonville Primary School that will be built on District property at 7151 SW Boeckman Road in the Frog Pond Neighborhood. The intent of this open house was to receive community feedback prior to designing the new school site both in person and by web survey. The district would like to extend this survey opportunity to community members who were not able to attend the open house.

    The survey includes questions regarding both site and building style or elements that might be desirable, as well as site layout and how the district can be a good neighbor. 

    The district does not currently have a design for the building or site and really appreciates hearing from the community with any hopes or concerns that people might have.

    To participate in our survey, follow this link.

    If you have any questions, please contact the Project Manager:

    Brooke Besheone

    besheonb@wlwv.k12.or.us

    503-673-7990

    Comments (-1)
  • 2022 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/28/2022

    Exterior New Storage Shed

    Recent Activities:
    ■ New School Pre-Design phase began in January and wrapped up in early March. Schematic Design phase started Mid March and continues into June
    ■ Geotechnical engineers did site testing for the new school site and are in the process of drafting the geotechnical report
    ■ The new storage building was completed and recieved temporary occupancy, full completion expected in late Spring


    Upcoming Activities:
    ■ New School Schematic Design phase meetings continue with district stakeholders and consultants
    ■ A community Open House for the new primary school to be held this Spring

    Comments (-1)
  • 2021 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/21/2022

    Recent Activities:
    ■ Building framing and siding complete
    ■ Building painting began
    ■ Parking lot graded for paving


    Upcoming Activities:
    ■ Completion of the storage building and all related site work
    ■ Pre-Design phase meetings begin with district stakeholders and consultants

    Shed Exterior

    Comments (-1)
  • 2021 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/21/2021

    Recent Activities:
    ■ Proposals turned in for a Design Concept Competition between two architecture firms on the program
    ■ Fencing being installed on new storage building site
    ■ New storage building being framed and parking lot graded
    ■ New water quality pond excavated and storm lines installed


    Upcoming Activities:
    ■ New storage building construction continuing including parking lot, landscaping and more fencing
    ■ Architecture proposals review and presentations. Firm selection Oct. 8th

    Comments (-1)
  • 2021 Quarter 1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/22/2021

    Recent Activities:
    ■ New storage building permit issued
    ■ New storage building contractor solicitation complete and contract has been fully executed
    ■ New storage building low bid below budget and estimate
    ■ New storage building general contractor mobilized and onsite


    Upcoming Activities:
    ■ New storage building construction continuing through the summer
    ■ New storage building environmental survey of existing structures on the new primary school site in Wilsonville

    Comments (-1)
  • Quarter 4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/2/2021

    Recent Activities:
    ■ New storage building Land Use CUP decision received
    ■ New Storage building out to bid January 2021


    Upcoming Activities:
    ■ Environmental survey of existing structures on new primary school site
    ■ Bids Due for new storage building late January 2021
    ■ Construction of new storage building anticipated Spring 2021
    ■ Develop logistics plan to ensure separation of construction and school activities