- 2019 Capital Bond
- Project Updates
WHS Performing Arts Center
Page Navigation
2021 Quarter 1 Project Updates
Posted by West Linn - Wilsonville School District on 4/22/2021
Recent Activities:
■ Construction Documents are approximately 65% complete and are currently under district review
■ Continuation of focus groups to discuss design details, including staff, students and community partners
■ Submitted for completeness review of Land Use Documentation
■ Pre-Qualification bidding strategy findings presented to the School Board and approved
Upcoming Activities:
■ General Contractor pre-qualification expected to launch in April
■ Finalize logistics package for construction
■ Final estimates expected in April
■ General contractor bids expected in June with construction anticipated to start in August