2021 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 8/4/2021

Recent Activities:
■ Bids were received end of June
■ Board approval to execute contract with low bidder, Todd Construction
■ Construction contract value is $27,834,000.00
■ Value engineering continuing on the project
■ First City of Wilsonville building permit review

Upcoming Activities:
■ Contractor mobilization to start early July
■ Site work anticipated once permitting is done, end of July
■ Front entry access expected to be restored prior to start of school