2022 Q1 Project Updates

Posted by West Linn - Wilsonville School District on 4/28/2022

View from auditorium stage

Recent Activities:
■ Main auditorium roof trusses are in place
■ Catwalks are being installed
■ Balcony steel is going in place
■ Weather proofing is being applied to exterior face of the building
■ Exploratory work for mechanical system connection to the new addition is taking place


Upcoming Activities:
■ Exterior brick to be installed
■ Mechanical, electrical and plumbing in the new lobby restrooms
■ Footings for both lobbies to be excavated and poured
■ Installation of sewer main relocation