2021 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 8/4/2021

Recent Activities:
■ Land Use Completeness memo received April 16th
■ Project deemed incomplete with six conditions of approval noted
■ All completeness items issued
■ Design Review Mitigation with Operations Staff held in May
■ Technology review sessions held with District IT staff including security, technolgoy and AV Systems
■ Interior color palette and finishes selected
■ Furniture vendor selected
■ Construction Document Phase estimate received
■ Land Use Hearing held July 7, continued to August 4

Upcoming Activities:
■ Construction Documents scheduled for completion in July
■ Submitting for building permit in July
■ Continued work with City of West Linn on Right of Way design

Library Rendering