- 2019 Capital Bond
- Project Updates
Athey Creek Middle School At Dollar
2022 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/22/2022
Recent Activities:
■ Grading for the building and lower parking lot is largely complete
■ The contractor fully mobilized to the site, using the lower parking area as staging for trailers and materials
■ The gym was fully excavated below Dollar Street and other areas of the building have been formed
■ Concrete pours have begun for structural footings
■ The large retaining wall that is parallel to Dollar Street was formed and poured
■ Underground utilities have been installed throughout the building footprint, including conduit for electrical rooms,
plumbing for restrooms as well as the main underground storm system
■ Grading for the upper parking lot has begun
■ The off-site permit for street work was approved by the City of West Linn
■ The relocation of PGE power poles has been completed
■ The appeal to the Land Use Board of Appeals decision was final April 18
Upcoming Activities:
■ Work on the north side of Willamette Falls Drive expected to start in July
■ Installation of interior CMU walls
■ Procurement of long lead items continues
■ Review of the furniture order to be finalized and an order is expected to be placed in the coming months
Recent
By Month
- April 2023
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- July 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- August 2021
- April 2021
- March 2021
- February 2021
- January 2021
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- February 2020