2022 Q2 Project Updates

Posted by West Linn - Wilsonville School District on 7/22/2022

Exterior Walls

Recent Activities:
■ Grading for the building and lower parking lot is largely complete
■ The contractor fully mobilized to the site, using the lower parking area as staging for trailers and materials
■ The gym was fully excavated below Dollar Street and other areas of the building have been formed
■ Concrete pours have begun for structural footings
■ The large retaining wall that is parallel to Dollar Street was formed and poured
■ Underground utilities have been installed throughout the building footprint, including conduit for electrical rooms,
plumbing for restrooms as well as the main underground storm system
■ Grading for the upper parking lot has begun
■ The off-site permit for street work was approved by the City of West Linn
■ The relocation of PGE power poles has been completed
■ The appeal to the Land Use Board of Appeals decision was final April 18

Upcoming Activities:
■ Work on the north side of Willamette Falls Drive expected to start in July
■ Installation of interior CMU walls
■ Procurement of long lead items continues
■ Review of the furniture order to be finalized and an order is expected to be placed in the coming months