- 2019 Capital Bond
- Project Updates
Athey Creek Middle School At Dollar
2022 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/26/2022
Recent Activities:
■ Final grading on the site bus entry, staff parking and track
■ All first floor concrete slabs have been poured and block wall installation is continuing.
■ Steel is on site for portions of the building and is currently being installed. This includes steel beams, trusses and one set of stairs.
■ The steel decking above the locker rooms, which creates the floor for the auxiliary gym, is installed.
■ The gym walls are complete, including the highest, poured in place wall along Dollar Street.
■ Rough installation of plumbing and electrical work is continuing.
■ An offsite tour was held to view the fabrication of the precast concrete walls. Delivery and installation of the precast members is expected to start the end of October.
■ Tree removal along Willamette Falls Drive occurred in July. The remaining work is expected in February.
■ Work began on Dollar Street with all construction parking moving onto the site.
■ The water line extension at Dollar Street is complete and the strom line is in process. Curbs are expected to be installed in October.
Upcoming Activities:
■ Precast concrete wall installation
■ Steel erection in the classroom wings
■ Temporary roof installation in certain sectors of the building
■ Paving on Dollar Street is scheduled for early November while Brandon Place will commence after Dollar Street is complete.
By Month
- March 2023
- February 2023
- December 2022
- November 2022
- October 2022
- July 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- August 2021
- April 2021
- March 2021
- February 2021
- January 2021
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- February 2020