2022 Q3 Project Updates

Posted by West Linn - Wilsonville School District on 10/26/2022

Exterior Construction walls

Recent Activities:
Final grading on the site bus entry, staff parking and track
■ All first floor concrete slabs have been poured and block wall installation is continuing.
Steel is on site for portions of the building and is currently being installed. This includes steel beams, trusses and one set of stairs.
■ The steel decking above the locker rooms, which creates the floor for the auxiliary gym, is installed.
■ The gym walls are complete, including the highest, poured in place wall along Dollar Street.
■ Rough installation of plumbing and electrical work is continuing.
■ An offsite tour was held to view the fabrication of the precast concrete walls. Delivery and installation of the precast members is expected to start the end of October.
■ Tree removal along Willamette Falls Drive occurred in July. The remaining work is expected in February.
■ Work began on Dollar Street with all construction parking moving onto the site. 
■ The water line extension at Dollar Street is complete and the strom line is in process. Curbs are expected to be installed in October.

Upcoming Activities: 
  Precast concrete wall installation
  Steel erection in the classroom wings
  Temporary roof installation in certain sectors of the building
  Paving on Dollar Street is scheduled for early November while Brandon Place will commence after Dollar Street is complete.