2022 Q1 Project Updates

Posted by West Linn - Wilsonville School District on 4/28/2022

Exterior New Storage Shed

Recent Activities:
■ New School Pre-Design phase began in January and wrapped up in early March. Schematic Design phase started Mid March and continues into June
■ Geotechnical engineers did site testing for the new school site and are in the process of drafting the geotechnical report
■ The new storage building was completed and recieved temporary occupancy, full completion expected in late Spring


Upcoming Activities:
■ New School Schematic Design phase meetings continue with district stakeholders and consultants
■ A community Open House for the new primary school to be held this Spring