2022 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/26/2022
Recent Activities:
■ New School Design Development phase completed in early September
■ Construction Document Design phase launched
■ Post-Covid-19 construction material availability/lead times have been assessed and a mock construction schedule was created to evaluate project timeline feasibility.
■ Meetings with district staff, students and parents were held to elicit feedback regarding the design
■ A second cost estimate has been received and value engineering efforts continue to reduce cost
■ A community open house was held in August
■ The new storage building is open and being used by district staff
Upcoming Activities:
■ New School Construction Document Design phase meetings with district stakeholders and consultants
■ General contractor qualifications process
■ Submit for land use with the City of Wilsonville