2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/2023
Recent Activities:
- New School Construction Development phase continues
- 60% design set being reviewed by the district
- After consideration of the previous quarters and Post COVID-19 construction material availability/lead times assessment, the decision was made to extend the construction schedule and therefore push the opening of the school to fall 2025
- Value engineering continues in efforts to bring cost within budget
- The project was submitted to the City of Wilsonville for Land Use approval in December
- General contractor pre-qualification proposals were received in December. An evaluation committee has reviewed and will release the qualified bidders list in January 2023
Upcoming Activities:
- New School Construction Document Design phase meetings with district stakeholders and consultants continue
- Continued work with the City of Wilsonville throughout Land Use to achieve approval
- Project goes out to bid in February for pre-qualified bidders
- Construction documents will be completed and submitted to the City of Wilsonville for the building permit review and approval