- 2019 Capital Bond
- Project Updates
2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023
Recent Actitives:
■ Final phase of conversion from Athey Creek Middle School to Riverside High School has begun
■ Athey Creek materials have been removed from the building
■ Demolition and site work is underway in the new CTE classroom spaces and outside the building
■ Gym bleachers have been removed and salvaged for materials
■ Furniture for the new Student Services Hub space has been delivered and assembled
Upcoming Activities:
■ Installation fo new gym bleachers, restriping and refinishing the gym floor to occur in August
■ Rough-in of mechanical, electrical and plumbing in the CTE spaces
■ Updating the library space with acoustical panels, paint and circulation desk
New library, lobby, commons and select classroom furniture will arrive late July and early August