• 2023 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/25/2024

    Recent Activities:

    • Project is complete
    Comments (-1)
  • 2023 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/31/2023

    library

    Recent Activities:
    ■    Project has reached substantial completion and is in closeout
    ■    Furniture has arrived and is in use by the school
    ■    Wall graphics installed
    ■    Gym floor refinished and new bleachers installed
    ■    ADA Ramp to the athletic field and track is complete

    Upcoming Activities:
    ■   Contractor punch list closeout items nearing completion

    Comments (-1)
  • Building Dedication Event

    Posted by West Linn - Wilsonville School District on 10/2/2023

    Dedication Invitation

    Comments (-1)
  • 2023 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/20/2023

    Construction Classroom

    Recent Actitives:
         Final phase of conversion from Athey Creek Middle School to Riverside High School has begun
         Athey Creek materials have been removed from the building
         Demolition and site work is underway in the new CTE classroom spaces and outside the building
         Gym bleachers have been removed and salvaged for materials
         Furniture for the new Student Services Hub space has been delivered and assembled

    Upcoming Activities:
         Installation fo new gym bleachers, restriping and refinishing the gym floor to occur in August
         Rough-in of mechanical, electrical and plumbing in the CTE spaces
         Updating the library space with acoustical panels, paint and circulation desk
    New library, lobby, commons and select classroom furniture will arrive late July and early August

    Comments (-1)
  • 2023 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/20/2023

    Recent Activities:
    Office remodel punchlist work is 99% complete
      The renovation for summer 2323 work to convert spaces to the new high school has been bid and a contract has been awarded.
      Partial furniture orders placed for the new high school spaces

    Upcoming Activities:
      Office remodel final punchlist items to be complete
      Empty current athy Creek Middle School and begin renovation summer 2023 for the school fall 2023.
      Continue to order equipment, furniture and supplies for Riverside High School.

    Comments (-1)
  • 2022 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/3/2023

    Recent Activities:

    • Office remodel punchlist work is 99% complete
    • The renovation for Summer 2023 work to convert spaces to the new high school has been bid and a contract has been awarded
    • Furniture orders placed for new high school spaces

    Upcoming Activities:

    • Office remodel final punchlist items to be complete
    • Empty current Athey Creek Middle School and begin renovation Summer 2023 for school fall 2023
    • Continue to order furniture and supplies for Riverside High School
    Comments (-1)
  • 2022 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/26/2022

    High School Entry

    Recent Activities:
    ■ Existing office space renovation is substantially complete.
    ■ Punch list progress
    ■ Design for Summer 2023 phase

    Upcoming Activities:
    ■ Complete design for Summer 2023 phase
    ■ Bid Summer 2023 phase this fall
    ■ Order furniture and supplies for Riverside High School

    Comments (-1)
  • Bond Construction Update: Riverside High School

    Posted by West Linn - Wilsonville School District on 8/3/2022

    See the latest work turning Athey Creek Middle School into the new Riverside High School and how the new classrooms are being built while not interrupting the learning of our middle school students.

    Comments (-1)
  • 2022 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/22/2022

    Office Construction

    Recent Activities:
    ■ Existing office space demolition is complete
    ■ Currently framing in single occupant restrooms and conference rooms
    ■ Mechanical, Electrical and Plumbing rough-in work has begun in the existing office space
    ■ Science hall roof well work has begun
    ■ Additional roof work and building envelope nearing completion
    ■ Punch list work has begun on new office space

    Upcoming Activities:
    ■ Substantial completion of current construction is expected at the
    end of August 2022
    ■ Design for final phase of work, scheduled for construction
    summer of 2023

    Comments (-1)
  • 2022 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/28/2022

    Exterior Building

    Recent Activities:
    ■ Staff has moved into the new office space
    ■ Commissioning of the mechanical systems is underway
    ■ Existing office space demolition work is underway
    ■ Concrete tile roof replacement is nearing completion

    Upcoming Activities:
    ■ Steel package installation for new mechanical unit over existing office space
    ■ Completion of interior finishes
    ■ Vestibule glass installation
    ■ Continued work in the existing office space

    Comments (-1)