- 2019 Capital Bond
- Project Updates
-
2023 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 1/25/2024Recent Activities:
- Project is complete
-
2023 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/31/2023Recent Activities:
■ Project has reached substantial completion and is in closeout
■ Furniture has arrived and is in use by the school
■ Wall graphics installed
■ Gym floor refinished and new bleachers installed
■ ADA Ramp to the athletic field and track is completeUpcoming Activities:
■ Contractor punch list closeout items nearing completion -
Building Dedication Event
Posted by West Linn - Wilsonville School District on 10/2/2023 -
2023 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023Recent Actitives:
■ Final phase of conversion from Athey Creek Middle School to Riverside High School has begun
■ Athey Creek materials have been removed from the building
■ Demolition and site work is underway in the new CTE classroom spaces and outside the building
■ Gym bleachers have been removed and salvaged for materials
■ Furniture for the new Student Services Hub space has been delivered and assembledUpcoming Activities:
■ Installation fo new gym bleachers, restriping and refinishing the gym floor to occur in August
■ Rough-in of mechanical, electrical and plumbing in the CTE spaces
■ Updating the library space with acoustical panels, paint and circulation desk
New library, lobby, commons and select classroom furniture will arrive late July and early August -
2023 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/20/2023Recent Activities:
■ Office remodel punchlist work is 99% complete
■ The renovation for summer 2323 work to convert spaces to the new high school has been bid and a contract has been awarded.
■ Partial furniture orders placed for the new high school spacesUpcoming Activities:
■ Office remodel final punchlist items to be complete
■ Empty current athy Creek Middle School and begin renovation summer 2023 for the school fall 2023.
■ Continue to order equipment, furniture and supplies for Riverside High School. -
2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/2023Recent Activities:
- Office remodel punchlist work is 99% complete
- The renovation for Summer 2023 work to convert spaces to the new high school has been bid and a contract has been awarded
- Furniture orders placed for new high school spaces
Upcoming Activities:
- Office remodel final punchlist items to be complete
- Empty current Athey Creek Middle School and begin renovation Summer 2023 for school fall 2023
- Continue to order furniture and supplies for Riverside High School
-
2022 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/26/2022Recent Activities:
■ Existing office space renovation is substantially complete.
■ Punch list progress
■ Design for Summer 2023 phaseUpcoming Activities:
■ Complete design for Summer 2023 phase
■ Bid Summer 2023 phase this fall
■ Order furniture and supplies for Riverside High School -
Bond Construction Update: Riverside High School
Posted by West Linn - Wilsonville School District on 8/3/2022See the latest work turning Athey Creek Middle School into the new Riverside High School and how the new classrooms are being built while not interrupting the learning of our middle school students.
-
2022 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/22/2022Recent Activities:
■ Existing office space demolition is complete
■ Currently framing in single occupant restrooms and conference rooms
■ Mechanical, Electrical and Plumbing rough-in work has begun in the existing office space
■ Science hall roof well work has begun
■ Additional roof work and building envelope nearing completion
■ Punch list work has begun on new office space
Upcoming Activities:
■ Substantial completion of current construction is expected at the
end of August 2022
■ Design for final phase of work, scheduled for construction
summer of 2023 -
2022 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/28/2022Recent Activities:
■ Staff has moved into the new office space
■ Commissioning of the mechanical systems is underway
■ Existing office space demolition work is underway
■ Concrete tile roof replacement is nearing completion
Upcoming Activities:
■ Steel package installation for new mechanical unit over existing office space
■ Completion of interior finishes
■ Vestibule glass installation
■ Continued work in the existing office space
Recent
-