2024 Q1 Project Updates

Posted by West Linn - Wilsonville School District on 4/23/2024

19029.007 – Boiler Replacement at Boones Ferry Primary School
Project Status: This project includes replacing the aging boilers with new energy-efficient boilers.


Recent Activities:
■    Project work will occur during the summer

 

19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.


Recent Activities:
■    Project bids were received
■    Board approval was given for the low bidder, First Cascade Corp
■    Project work will occur during the summer

 

19063.001 – Security Hardware at West Linn High School
Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.


Recent Activities:
■    Project bids were received
■    Board approval was given for the low bidder, Ross Builders Northwest LLC
■    Project work will occur during the summer

 

19064.021 – Track Replacement at Rosemont Ridge Middle School
Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.


Recent Activities:
■    Board approval was given to Beynon Sports
■    Project work will occur during the summer