• 2024 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 11/19/2024

    19029.007 – Boiler Replacement at Boones Ferry Primary School

    Recent Activities:
    ■ The boilers have been installed and are awaiting commissioning. Temporary heating measures are in place until commissioning completes in October

    19061.020 – Rewiring at Willamette Primary School

    Recent Activities:
    ■ Project is complete


    19063.001 – Security Hardware at West Linn High School

    Recent Activities:
    ■ The project is substantially complete. Final review of hardware locations is underway.


    19064.021 – Track Replacement at Rosemont Ridge Middle School
    Recent Activities:
    ■ Project is complete, track is open

     

    Comments (-1)
  • 2024 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/30/2024

    19029.007 – Boiler Replacement at Boones Ferry Primary School

    Recent Activities:
    ■    The mechanical contractor started demo of the old boilers once school released for the summer
    ■    New piping is currently being fabricated in preparation for the arrival of the new boilers at the end of July
    ■    The building is fully functional while construction is underway

     

    19061.020 – Rewiring at Willamette Primary School

    Recent Activities:
    ■    Demolition of the existing wiring began once school released for the summer
    ■    The school is closed as work continues rewiring. The project is expected to be complete prior to the start of school

     

    19063.001 – Security Hardware at West Linn High School

    Recent Activities:
    ■    New hardware has been delivered to the school and electrical work is being completed prior to hardware instal-lation
    ■    The district is working with the contractor to re-key the entire building

     

    19064.021 – Track Replacement at Rosemont Ridge Middle School

    Recent Activities:
    ■    Demolition of the existing track began after the Memorial Day Holiday.
    ■    The track closed for the month of June to allow for replacement and striping
    ■    Work is complete and contractor is removing fencing to allow for community use in July

    Comments (-1)
  • 2024 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/23/2024

    19029.007 – Boiler Replacement at Boones Ferry Primary School
    Project Status: This project includes replacing the aging boilers with new energy-efficient boilers.


    Recent Activities:
    ■    Project work will occur during the summer

     

    19061.020 – Rewiring at Willamette Primary School
    Project Status: This project includes replacing all network cabling and relocating wiring closets.


    Recent Activities:
    ■    Project bids were received
    ■    Board approval was given for the low bidder, First Cascade Corp
    ■    Project work will occur during the summer

     

    19063.001 – Security Hardware at West Linn High School
    Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.


    Recent Activities:
    ■    Project bids were received
    ■    Board approval was given for the low bidder, Ross Builders Northwest LLC
    ■    Project work will occur during the summer

     

    19064.021 – Track Replacement at Rosemont Ridge Middle School
    Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.


    Recent Activities:
    ■    Board approval was given to Beynon Sports
    ■    Project work will occur during the summer

    Comments (-1)
  • 2023 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/25/2024

    19029.007 – Boiler Replacement at Boones Ferry Primary School


    Project Status: This project includes replacing the aging boilers with new energy efficient boilers.


    Recent Activities:
    ■    Project bids were received.
    ■    Board approval was given for the low bidder Copper Mechanical to proceed
    ■    Contract is out for signature

     

    19061.020 – Rewiring at Willamette Primary School
    Project Status: This project includes replacing all network cabling and relocating wiring closets.


    Recent Activities:
    ■    Project is out to bid. Bids are due January 11th.

    19063.001 – Security Hardware at West Linn High School


    Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.


    Recent Activities:
    ■    Project is out to bid. Bids are due January 24th.

     

    19064.021 – Track Replacement at Rosemont Ridge Middle School

     Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.


    Recent Activities:
    ■    Project is in review and preparing for pricing

     

    Comments (-1)
  • 2023 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/31/2023

    19039.018 – Security Upgrades at Trillium Creek Primary School
    Project Status:
    This project includes creating a secure entry vestibule and improved classroom lockdown capability.
    Recent Activities:
    ■     Project has reached substantial completion and is in closeout

    19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools Project Status:
    This project includes security curtains and improved classroom lockdown capabilities at these three schools.
    Recent Activities:
    ■     Project has reached substantial completion and is in closeout

    9029.007 – Boiler Replacement at Boones Ferry Primary School Project Status:
    This project includes replacing the aging boilers with new energy efficient boilers.
    Recent Activities:
    ■     Project is in review and preparing to bid

    19061.020 – Rewiring at Willamette Primary School
    Project Status:
    This project includes replacing all network cabling and relocating wiring closets.
    Recent Activities:
    ■     Project is in review and preparing to bid

    19063.001 – Security Hardware at West Linn High School
    Project Status:
    This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
    Recent Activities:
    ■     Project is in review and preparing to bid

    19064.021 – Track Replacement at Rosemont Ridge Middle School Project Status:
    This project includes track resurfacing at Rosemont Ridge Middle School.
    Recent Activities:
    ■     Project is in review and preparing to bid

    Comments (-1)
  • 2023 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 7/20/2023

    Front Office Renovation

    Security Upgrades at Trillium Creek Primary School

    Recent Activities:
         Office has been cleared and ready for work
         Electrical rough-in for the new security systems is underway

    Upcoming Activities:
         Demoltion and construction of the secure entry vestibule
         Installation of school side door hardware upgrade and classroom security curtains

    Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools

    Recent Activities:
         Project window film installation has begun

    Upcoming Activities:
         Installation of classroom security curtains to start in the coming weeks at all three schools

    Comments (-1)
  • 2023 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/20/2023

    19039.018 Security Upgrades at Trillium Creek Primary School
    Recent Activities:
      This project has bid and has an executed contract in place.
    Upcoming Activities:
      Work to begin summer 2023

    19059.009 Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools
    Recent Activieis:
      This project has bid and has an executed contract in place.
    Upcoming Activities:
      Work to begin summer 202

    Comments (-1)
  • 2022 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/3/2023

    19039.018 – Security Upgrades at Trillium Creek Primary School

    Project Status:

    This project includes creating a secure entry vestibule and improved classroom lockdown capability.

     Recent Activities:

    • This project bid and has an executed contract in place, work to begin summer 2023

     

    19054.017 – Fire Sprinklers at Boeckman Creek Primary School

    Project Status:

    This project includes fire sprinkler main line replacement at Boeckman Creek Primary School.

     Recent Activities:

    • This project is complete. Final testing occurred and is complete.

     

    19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools

    Project Status:

    This project includes security curtains and improved classroom lockdown capabilities at these three schools.

     Recent Activities:

    • The project is currently in design

    Upcoming Activities:

    • Bidding in Spring 2023 with construction to occur Summer 2023
    Comments (-1)
  • 2022 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/26/2022

    19034.011 – Renovation at Wood Middle School
    Recent Activities:
    ■ This project is complete

    19054.017 - Fire Sprinklers at Boeckman Creek Primary School
    Recent Activities:
      This project is substantially complete. Final testing and addressing minor leaks in existing portions of the system will continue through the Fall, outside of school hours.

    19057.009 - Recabling Project at Boeckman Creek and Stafford Primary Schools
    Recent Activities:
      This project is substantially complete.

    Comments (-1)
  • 2022 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/22/2022

    19034.011 – Renovation at Wood Middle School
    Recent Activities:
    ■ Digital street sign installed
    ■ Final punchlist work is nearing completion, all construction fencing has been removed and the building has
    been turned over to the school

    Upcoming Activities:
    ■ Final payment and closeout

    19053.017 – Roofing at Boeckman Creek Primary School
    Project Status:
    This project is on hold.


    19054.017 – Fire Sprinklers at Boeckman Creek Primary School
    Project Status:
    This project includes fire sprinkler main line replacement at Boeckman Creek Primary School.
    This project was bid and awarded to Brockamp & Jaeger Inc. Work started in late June after school was released for the summer. Work will continue through the summer and be done before the start of school. No material delays are expected as part of this project.


    19057.009 – Recabling Project at Boeckman Creek and Stafford Primary Schools
    Project Status:
    This project includes recabling to update to CAT 6 and 6A at both Boeckman Creek and Stafford Primary Schools.
    This project was bid and awarded to Brockamp & Jaeger Inc. Work started in late June after school was released for the summer. Work will continue through the summer and be done before the start of school. No material delays are expected as part of this project.

    Comments (-1)