• 2021 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 8/4/2021

    19034.011 – Renovation at Wood Middle School
    Project Status:
    Light renovation through various parts of the school, total renovation of front classroom cluster, relocation of office and creation of maker space and a restroom/concessions building addition. Design includes security upgrades, energy efficiency improvements, and the life cycle replacement of mechanical and fire alarm systems.

    Inza Wood Interior

    Contractor mobilization began early, utilizing after school hours. Contractor has focused attention on all interior school scope of work to ensure readiness for students return in the fall. Areas currently being demolished include the old administration offices and classrooms on the Northeast side of the building. Classrooms on the Southwest side of the building have been demolished and are in plumbing, mechanical, and structure phases. Roof work above the main gym is in process including removing the old mechanical units and constructing a new roof diaphragm. Excavation is underway for the new restroom and concession addition as well as the new greenhouse.

    19049.009 – Renovations at Stafford Primary School & Willamette Primary School
    Project Status:
    Construction began at the end of June. Recent work at Stafford includes abatement at the kitchen, demolition for HVAC above classroom spaces and electrical and carpentry working on new rooftop units. At Willamette work at the front entry has begun as well as HVAC, controls and electrical demo inside. Storm drain work along 12th Street is underway.

    Willamette Entry


    19050.009 – Renovations at Bolton Primary School and Cedaroak Park Primary School
    Project Status:
    Construction began at the end of June. Recent work at Bolton includes electrical and HVAC demo as well as rough in carpentry for both upper and lower classrooms. Cedaroak exterior painting has begun and ductwork cleaning, water heater demo and plumbing getting underway.

    Comments (-1)
  • 2021 Quarter 1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/22/2021

    19034.011 – Renovation at Wood Middle School
    Project Status:
    Project has been advertised and awarded. Contractor mobilization is expected spring 2021. Logistics planning to ensure separation of construction and school activities underway.
    ■ Low bid below budget and estimate
    ■ Board authorized selection of all project scope

    19049.009 – Renovations at Stafford Primary School & Willamette Primary School
    Project Status:
    The project was bid and a general contractor was awarded the project in February. The low bid was over budget but near the estimate. The School Board authorized selection of the base bid. This project is scheduled to start construction this summer.

    19050.009 – Renovations at Bolton Primary School and Cedaroak Park Primary School
    Project Status:
    The project was bid and a general contractor was awarded the project in February. The low bid was over budget but near the estimate. The School Board authorized selection of the base bid. This project is scheduled to start construction this summer.

     

    Comments (-1)
  • Quarter 4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/2/2021

    19034.011 – Renovation at Wood Middle School
    Project Status: Light renovation through various parts of the school, total renovation of front classroom cluster, relocation of office and creation of maker space and a restroom/concessions building addition. Design includes security upgrades, energy efficiency improvements, and the life cycle replacement of mechanical and fire alarm systems.

    Project design has been completed and will go out for bid January 2021. Anticipated contract award February 2021 with construction activities planned during summer and fall 2021. Logistics planning to ensure separation of construction and school activities underway.

     Wood Entry Rendering


    19042.019 Sports Field Relighting at Wilsonville High School
    Project Status: Project is complete.

    19044.009 – Security @ COP, RR, ST
    Project Status: This project includes security upgrades at these three schools. The work has been designed, bid and the work is underway. The work is substantially complete.

    19045.009 – Security @ BF, LW
    Project Status: This project includes security upgrades at these two schools. The work has been designed, bid and the work is underway. The work is substantially complete.

    Stafford Entry

    19048.009 – Renovations at Bolton Primary School and Cedaroak Park Primary School
    Project Status: This project includes classroom air conditioning, security improvements and other life cycle replacement work. Project will go out to bid late January with construction scheduled over summer 2021.

    19049.009 – Renovations at Stafford Primary School and Willamette Primary School
    Project Status: This project includes classroom air conditioning, security improvements and other life cycle replacement work. Also includes a new accessible and secure entry for Willamette Primary School. Project will go out to bid late January with construction scheduled over summer 2021.

    Willamette Primary Rendering

    Comments (-1)
  • Quarter 3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/28/2020

    Renovation at Inza Wood Middle School

    Project Status: The project is scheduled for construction summer and fall 2021. It is currently in the Design Development phase and is being reviewed by district leadership. 

     

    Sports Field Relighting at Wilsonville High School

    Project Status: The onsite work is complete and closeout documentation is underway. 

    WHS lighting at night

     

    Track Replacement at Athey Creek Middle School

    Project status: Project is complete

     

    Security @ Boones Ferry and Lowrie Primary Schools

    Project Status: This project has been designed, bid, and the work is underway and substantially complete. 

     

    Security @ Cedaroak Park Primary, Rosemont Ridge Middle and Stafford Primary Schools

    Project Status: This project has been designed, bid, and the work is underway and substantially complete. 

    Rosemont entry

     

    Flooring at Stafford

    Project Status: This project is complete

     

    Mechanical at West Linn High and Willamette Primary Schools

    Project Status: This project is complete

     

    Renovations @ Bolton and Cedaroak Park Primary Schools

    Project Status: This project includes classroom air conditioning, security improvements and other life cycle replacement work. Design is currently underway with an expected construction start summer 2021. 

     

    Renovations at Stafford and Willamette Primary Schools

    Project Status: This project includes classroom air conditioning, security improvements and other life cycle replacement work. Design is currently underway with an expected construction start summer 2021. 

     

    Comments (-1)
  • Improvements at Inza R. Wood Middle School

    Posted by West Linn - Wilsonville School District on 9/25/2020 10:25:00 AM

    Design and planning are steadily progressing for renovations at Wood Middle School. Improvements will include security upgrades, a new CTE (career and technical education) makerspace classroom, LED lighting improvements, gym roof replacement, mechanical system replacements and a restroom/concessions building addition. Design Completion is anticipated for November 2020, with construction beginning Summer 2021.

    Exterior Wood Entry

    Comments (-1)
  • Summer 2020 Mechanical Upgrades

    Posted by West Linn - Wilsonville School District on 9/25/2020 10:00:00 AM

    Boiler Replacement at WLHS

    This summer, replacement occurred of an existing boiler at West Linn H.S. that had previously been in failure. Tied into the building’s automated control system, the new boiler will provide reliability and increased energy efficiency.

    RTU Replacement at Willamette Primary

    This summer, replacement occurred for one existing gas-fired makeup air unit on top of the Willamette Primary Gymnasium.

    Comments (-1)
  • Summer Security Projects Update

    Posted by West Linn - Wilsonville School District on 9/2/2020

    Stafford Primary, Cedaroak Park Primary and Rosemont Ridge Middle School Project update:

    General Site Work:

    • All office interior changes are nearing completion.
    • Electronic safety systems installation is also near completion as is new access control measures being installed at main school entrances.
    • New carpet and interior paint at the three schools are also looking great and nearing completion.

    If you have any questions, please contact the Project Manager.

     

    Kevin Warren

    warrenk@wlwv.k12.or.us

     

    Comments (-1)
  • 2nd Quarter Project Updates

    Posted by Amy Berger on 8/5/2020

    19034.011 – Renovation at Wood Middle School
    Project Status:
    Light renovation through various parts of the school, total renovation of front classroom cluster, relocation of office and
    creation of new classrooms and maker space. Energy efficiency upgrades, life cycle replacement and the addition of an
    educational greenhouse.
    This project is scheduled for construction during the summer and fall 2021.
    The project is in the Design Development stage of design.

    Light pole      19042.019 Sports Field Relighting at Wilsonville High School 
         Project Status:
         Sports field lighting replacement for the stadium, baseball fields and three tennis courts. The varsity softball field has already received this upgrade, and the JV softball field will receive the upgrade as part of another project. The contractor is on board, and most of the work has been completed. The final two fixtures will be replaced this fall, when Osprey are absent from this location.

     

    19043.006 - Track Replacement at Athey Creek Middle School Track
    Project Status:
    This project is substantially complete.

    19045.009 – Security @ BF, LW
    Project Status:
    This project includes security upgrades at these two
    schools. The work has been design, bid and the work
    is underway. The work is expected to be substantially
    complete for the start of the school year in August 2020.

         19044.009 – Security @ COP, RR, ST  Secure Entry
         Project Status:
         This project includes security upgrades at these three
         schools. The work has been design, bid and the work is
         underway. The work is expected to be substantially complete
         for the start of the school year in August 2020.

    19046.004 – Flooring @ ST  Flooring
    Project Status:
    This project includes the abatement of existing
    flooring materials, and the installation of new
    carpet and vinyl flooring for classrooms and support
    spaces. The abatement is complete and installation
    of the flooring is underway.


    19048.009 – Mechanical @ WLHS, WM
    Project Status:
    This project includes a boiler replacement at West Linn High
    School and the gym mechanical unit replacement at Willamette
    Primary School. This equipment was routinely failing and so
    immediate replacement is underway. The project has been
    designed, bid and is underconstruction in preparation for start
    of school this fall.


    19049.009 – Renovations at Bolton Primary School and Cedaroak Park Primary School  
    Project Status:
    This project includes classroom air conditioning,
    security improvements and other life cycle replacement
    work. Design is currently underway with an expected
    construction start in summer 2021.


    19050.009 – Renovations at Stafford Primary School and Willamette Primary School
    Project Status:
    This project includes classroom air conditioning,
    security improvements and other life cycle replacement
    work. Design is currently underway with an expected
    construction start in summer 2021.