- 2019 Capital Bond
- Project Updates
Facility Updates











-
2024 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 11/19/202419029.007 – Boiler Replacement at Boones Ferry Primary School
Recent Activities:
■ The boilers have been installed and are awaiting commissioning. Temporary heating measures are in place until commissioning completes in October19061.020 – Rewiring at Willamette Primary School
Recent Activities:
■ Project is complete
19063.001 – Security Hardware at West Linn High School
Recent Activities:
■ The project is substantially complete. Final review of hardware locations is underway.
19064.021 – Track Replacement at Rosemont Ridge Middle School
Recent Activities:
■ Project is complete, track is open -
2024 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/30/202419029.007 – Boiler Replacement at Boones Ferry Primary School
Recent Activities:
■ The mechanical contractor started demo of the old boilers once school released for the summer
■ New piping is currently being fabricated in preparation for the arrival of the new boilers at the end of July
■ The building is fully functional while construction is underway19061.020 – Rewiring at Willamette Primary School
Recent Activities:
■ Demolition of the existing wiring began once school released for the summer
■ The school is closed as work continues rewiring. The project is expected to be complete prior to the start of school19063.001 – Security Hardware at West Linn High School
Recent Activities:
■ New hardware has been delivered to the school and electrical work is being completed prior to hardware instal-lation
■ The district is working with the contractor to re-key the entire building19064.021 – Track Replacement at Rosemont Ridge Middle School
Recent Activities:
■ Demolition of the existing track began after the Memorial Day Holiday.
■ The track closed for the month of June to allow for replacement and striping
■ Work is complete and contractor is removing fencing to allow for community use in July -
2024 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/23/202419029.007 – Boiler Replacement at Boones Ferry Primary School
Project Status: This project includes replacing the aging boilers with new energy-efficient boilers.
Recent Activities:
■ Project work will occur during the summer19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■ Project bids were received
■ Board approval was given for the low bidder, First Cascade Corp
■ Project work will occur during the summer19063.001 – Security Hardware at West Linn High School
Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■ Project bids were received
■ Board approval was given for the low bidder, Ross Builders Northwest LLC
■ Project work will occur during the summer19064.021 – Track Replacement at Rosemont Ridge Middle School
Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■ Board approval was given to Beynon Sports
■ Project work will occur during the summer -
2023 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 1/25/202419029.007 – Boiler Replacement at Boones Ferry Primary School
Project Status: This project includes replacing the aging boilers with new energy efficient boilers.
Recent Activities:
■ Project bids were received.
■ Board approval was given for the low bidder Copper Mechanical to proceed
■ Contract is out for signature19061.020 – Rewiring at Willamette Primary School
Project Status: This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■ Project is out to bid. Bids are due January 11th.19063.001 – Security Hardware at West Linn High School
Project Status: This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■ Project is out to bid. Bids are due January 24th.19064.021 – Track Replacement at Rosemont Ridge Middle School
Project Status: This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■ Project is in review and preparing for pricing -
2023 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/31/202319039.018 – Security Upgrades at Trillium Creek Primary School
Project Status:
This project includes creating a secure entry vestibule and improved classroom lockdown capability.
Recent Activities:
■ Project has reached substantial completion and is in closeout19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools Project Status:
This project includes security curtains and improved classroom lockdown capabilities at these three schools.
Recent Activities:
■ Project has reached substantial completion and is in closeout9029.007 – Boiler Replacement at Boones Ferry Primary School Project Status:
This project includes replacing the aging boilers with new energy efficient boilers.
Recent Activities:
■ Project is in review and preparing to bid19061.020 – Rewiring at Willamette Primary School
Project Status:
This project includes replacing all network cabling and relocating wiring closets.
Recent Activities:
■ Project is in review and preparing to bid19063.001 – Security Hardware at West Linn High School
Project Status:
This project includes improved classroom lockdown hardware capabilities, in line with those installed at all district schools.
Recent Activities:
■ Project is in review and preparing to bid19064.021 – Track Replacement at Rosemont Ridge Middle School Project Status:
This project includes track resurfacing at Rosemont Ridge Middle School.
Recent Activities:
■ Project is in review and preparing to bid -
2023 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 7/20/2023Security Upgrades at Trillium Creek Primary School
Recent Activities:
■ Office has been cleared and ready for work
■ Electrical rough-in for the new security systems is underwayUpcoming Activities:
■ Demoltion and construction of the secure entry vestibule
■ Installation of school side door hardware upgrade and classroom security curtainsSecurity Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools
Recent Activities:
■ Project window film installation has begunUpcoming Activities:
■ Installation of classroom security curtains to start in the coming weeks at all three schools -
2023 Q1 Project Updates
Posted by West Linn - Wilsonville School District on 4/20/202319039.018 Security Upgrades at Trillium Creek Primary School
Recent Activities:
■ This project has bid and has an executed contract in place.
Upcoming Activities:
■ Work to begin summer 202319059.009 Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools
Recent Activieis:
■ This project has bid and has an executed contract in place.
Upcoming Activities:
■ Work to begin summer 202 -
2022 Q4 Project Updates
Posted by West Linn - Wilsonville School District on 2/3/202319039.018 – Security Upgrades at Trillium Creek Primary School
Project Status:
This project includes creating a secure entry vestibule and improved classroom lockdown capability.
Recent Activities:
- This project bid and has an executed contract in place, work to begin summer 2023
19054.017 – Fire Sprinklers at Boeckman Creek Primary School
Project Status:
This project includes fire sprinkler main line replacement at Boeckman Creek Primary School.
Recent Activities:
- This project is complete. Final testing occurred and is complete.
19059.009 – Security Upgrades at Meridian Creek Middle, Sunset Primary and West Linn High Schools
Project Status:
This project includes security curtains and improved classroom lockdown capabilities at these three schools.
Recent Activities:
- The project is currently in design
Upcoming Activities:
- Bidding in Spring 2023 with construction to occur Summer 2023
-
2022 Q3 Project Updates
Posted by West Linn - Wilsonville School District on 10/26/202219034.011 – Renovation at Wood Middle School
Recent Activities:
■ This project is complete19054.017 - Fire Sprinklers at Boeckman Creek Primary School
Recent Activities:
■ This project is substantially complete. Final testing and addressing minor leaks in existing portions of the system will continue through the Fall, outside of school hours.19057.009 - Recabling Project at Boeckman Creek and Stafford Primary Schools
Recent Activities:
■ This project is substantially complete. -
2022 Q2 Project Updates
Posted by West Linn - Wilsonville School District on 7/22/202219034.011 – Renovation at Wood Middle School
Recent Activities:
■ Digital street sign installed
■ Final punchlist work is nearing completion, all construction fencing has been removed and the building has
been turned over to the school
Upcoming Activities:
■ Final payment and closeout19053.017 – Roofing at Boeckman Creek Primary School
Project Status:
This project is on hold.
19054.017 – Fire Sprinklers at Boeckman Creek Primary School
Project Status:
This project includes fire sprinkler main line replacement at Boeckman Creek Primary School.
This project was bid and awarded to Brockamp & Jaeger Inc. Work started in late June after school was released for the summer. Work will continue through the summer and be done before the start of school. No material delays are expected as part of this project.
19057.009 – Recabling Project at Boeckman Creek and Stafford Primary Schools
Project Status:
This project includes recabling to update to CAT 6 and 6A at both Boeckman Creek and Stafford Primary Schools.
This project was bid and awarded to Brockamp & Jaeger Inc. Work started in late June after school was released for the summer. Work will continue through the summer and be done before the start of school. No material delays are expected as part of this project.