• 2023 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/20/2023

    Recent Activities:
      Project is Complete

    Comments (-1)
  • 2022 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 2/3/2023

    Recent Activities:

    • Concrete work occurred over winter break and will continue as weather allows

     Upcoming Activities:

    • Completion of concrete work
    Comments (-1)
  • 2022 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/26/2022

    Sunset view from stadium

    Recent Activities:
      Final occupancy from the City of West Linn was received
    ■. The stadium is open and being used for events
      The new AV system is fully functioning and being utilized for events

    Upcoming Activities:
      Concrete punch list items are expected to be completed during winter break

    Comments (-1)
  • Bond Construction Update: West Linn High School

    Posted by West Linn - Wilsonville School District on 8/23/2022

    See the latest work being done at West Linn High School that is expanding and improving the stadium as well as building a new parking lot with nearly 100 new spaces for students this school year.

    Comments (-1)
  • 2022 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 7/22/2022

    WLHS Drone Image

    Recent Activities:
    ■ The new parking lot opened for use at the end of May
    ■ All landscaping and bark installation is complete
    ■ Concrete ramps were completed and opened for use in the Spring
    ■ The concessions area has been completed and open for use
    ■ The final concrete sections are completed as the contractor continues to work through the punch list
    ■ The contractor is completing handrail installation at the ramps


    Upcoming Activities:
    ■ Final handrail installation and project closeout

    Comments (-1)
  • 2022 Q1 Project Updates

    Posted by West Linn - Wilsonville School District on 4/28/2022

    New Parking Lot

    Recent Activities:
    ■ Temporary Occupancy was received from the City of West Linn in March
    ■ Concrete layout in the upper plaza continues and curved walls have been poured
    ■ Landscape installation is in progress
    ■ Drainage has been incorporated into the parking lot and paving is being scheduled
    ■ New Audio Visual system is installed and press boxes are being used
    ■ Games are being played on the field and the stadium seating is being used


    Upcoming Activities:
    ■ Paving of the new parking lot is scheduled for April
    ■ The connection of the new walking path to the crosswalk of the upper north lot continues
    ■ Handrails, landscaping and items for final occupancy are in progress

    Comments (-1)
  • 2021 Q4 Project Updates

    Posted by West Linn - Wilsonville School District on 1/21/2022

    Recent Activities:
    ■ Stadium roof structure is complete
    ■ Concrete layout in the upper plaza continues and curved walls have been poured
    ■ The new parking lot curbs, light pole bases, and irrigation is complete
    ■ Storm drain detention system tanks in the upper plaza are complete
    ■ New stadium seating is complete and handrail installation has begun
    ■ Components for the new audio-visual system have arrived and are being installed


    Upcoming Activities:
    ■ Paving of the new parking lot will occur when weather allows
    ■ Storm drain tanks in the lower plaza
    ■ The parking lot, stadium and upper plaza are anticipated to be turned over to the district at the end of February
    ■ The contractor will be working with the City to obtain temporary occupancy

    WLHS Parking Ariel

    Comments (-1)
  • WLHS Stadium Project Update

    Posted by West Linn - Wilsonville School District on 11/15/2021

    WLHS STADIUM & PARKING EXPANSION – PROJECT UPDATE

    Air photo of site

    Raising the Roof! There have been product delays that have kept the stadium from completing in October as originally scheduled, however the project is moving forward. The stadium roof structure shipped in from Idaho, and the installation of the sheet metal roofing is near completion. The new restrooms, stadium seating, and updated press rooms are all getting finishing touches. The field lights have been operational since September, which has allowed evening soccer and other games to occur.

    The addition of storm drain work in the bus loop consumed contractor resources and shifted the priority toward the reopening of the bus loop in time for school to start. Though the contractors did make the bus loop deadline the ability to concurrently complete the stadium in time for football playoffs did not materialize.

    The new parking lot and plaza have a subterranean drainage system consisting of a series of tanks. These tanks were delayed which led to a series of design changes and ultimately, schedule loss. This new system is designed to intercept and treat rain water from the parking lot and hillside, which will not only clean water return to the river but prevent it from streaming into the stadium and track.

    When the parking lot is complete it will be connected to the stadium with a new plaza which will provide new spaces for students during the school day and the community to gather during sporting events. The General Contractor continues to try and improve the schedule with creative means.

    Comments (-1)
  • 2021 Q3 Project Updates

    Posted by West Linn - Wilsonville School District on 10/21/2021

    Aerial Photo of stadium and new courtyard

    Recent Activities:
    ■ Bus loop storm drain installation complete and opened on time for school
    ■ Concrete stadium step installation complete, plaza work began in September
    ■ New stadium seating was installed on the north side of the field
    ■ Stadium field lighting was completed in September
    ■ Working on contracting for a new fire alarm system for the stadium


    Upcoming Activities:
    ■ Stadium steel roof beams and columns arriving for install in October
    ■ Parking lot asphalt scheduled for mid November
    ■ Parking lot completion scheduled for early December
    ■ New audio-visual system to be installed

    Aerial photo of new parking lot and plaza

    Comments (-1)
  • 2021 Q2 Project Updates

    Posted by West Linn - Wilsonville School District on 8/4/2021

    Recent Activities:
    ■ Notice to proceed issued to contractor in April
    ■ Contractor began early site mobilization late April
    ■ Parking lot, plaza and stadium seating work began
    ■ Storm drain work in the bus loop to began re-route the storm line
    ■ Building permit received late June
    ■ Work fully underway after release of school for the summer late June

    Upcoming Activities:
    ■ Work on the corner of West A Street and Skyline scheduled for completion in July
    ■ Added work in the bus loop scheduled for completion prior to start of school
    ■ Stadium seating area scheduled for completion end of September
    ■ Completion of the Parking lot and Plaza scheduled for October

    Ariel photo of construction

    Comments (-1)